McClure and Sons Inc. 3/1/2017 Change Order 1
>
Contracts
>
Capital Contract
>
McClure and Sons Inc. 3/1/2017 Change Order 1
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/23/2017 1:45:17 PM
Creation date
3/23/2017 1:45:14 PM
Metadata
Fields
Template:
Contracts
Contractor's Name
McClure and Sons Inc.
Approval Date
3/1/2017
Department
Public Works
Department Project Manager
Amie Roshak
Subject / Project Title
UP3583 Puget Sound Outfall No. 6 Reroute
Amendment/Change Order
Change Order
Amendment/Change Order Number
1
Tracking Number
0000178
Total Compensation
$91,109.01
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
McClure and Sons Inc. 7/25/2016
(Amendment)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
8
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Project: Puget Sound Outfall No. 6 Reroute <br /> Change Order No. 1 <br /> Change Order Effective Date: February 1, 2017 <br /> 4. The duration of the Contract shall be adjusted to the extent described in this Change <br /> Order. <br /> 5. Contractor waives and releases any and all claims arising out of, or related to, this <br /> Change Order, the work described in Exhibit A, and all work and actual or constructive <br /> changes that occurred or began,prior to the date of this Change Order, including, but <br /> not limited to, claims for equitable adjustment of time and compensation, delay,impact, <br /> overhead, or inefficiencies. This provision does not apply to requests for equitable <br /> adjustment of time or price for which the Contractor timely and properly provided <br /> notice of a differing site condition,protest, dispute, claim or Contract Claim as required <br /> by the Contract Documents. If the Contract Documents establish a time period for <br /> notice of a differing site condition,protest, 'dispute, claim, or Contract Claim that ends <br /> after the date of this Change Order, but relates to work performed prior to the date of <br /> this Change Order, then this provision does not apply if the Contractor timely and <br /> properly submits such notice <br /> 6. This Change Order only changes the contract between Contractor and City to the <br /> extent explicitly provided herein. <br /> CITY <br /> Attest: Approved As to Form: ?' <br /> M ' / City Clerk - City Attorney <br /> Da •. Date: 3-1 -A017 • 31 /l/ <br /> Recommended By: <br /> Construction Project Engineer (if Engineering Department Director <br /> Manager(if applicable) Manager(if <br /> applicable) applicable) <br /> I, /,6 <br /> Date: 2 2 z. /7 Date: 2/Z 21/7 Date: Date: • (-7 <br /> CONTRACTOR <br /> (64,4 <br /> Officer Date: 2-14-7 <br /> • <br /> Page 2 of 3 <br />