Project: Puget Sound Outfall No. 6 Reroute <br /> Change Order No. 1 <br /> Change Order Effective Date: February 1, 2017 <br /> Exhibit A—Description of Changed Work: <br /> The developed scope and design, drawings G1.0 to C1.3 issued for construction 12/2016, were provide <br /> by the Port of Everett and are Port Additional Work. <br /> A new Schedule B will be created for Port Additional Work comprised of the following: <br /> New Item B.1 - Pavement Removal,New Pipe and Structure Installation,Concrete Plug. Create <br /> New Item B.1 entitled"Pavement Removal,New Pipe and Structure Installation, Concrete Plug",to <br /> provide funds at Lump Sum price of$39,230.00 resulting in an increase of$39,230.00 to the contract. <br /> New Item B.2 - CDF for Pipe/Structure in place Abandonment. Create New Item B.2 entitled <br /> "CDF for Pipe/Structure in place Abandonment", to provide funds at unit price of$158.00 per CY at <br /> an estimated quantity of 125 CY of"CDF for Pipe/Structure in place Abandonment", resulting in an <br /> increase of$19,750.00 to the contract. <br /> New Item B.3 -Asphalt Pavement Patch. Create New Item B3 entitled"Asphalt Pavement Patch", <br /> to provide funds at unit price of$150.00 per TN at an estimated quantity of 160 TN of"Asphalt <br /> Pavement Patch",resulting in an increase of$24,000.00 to the contract. <br /> New Item B.4 -Pipe Bedding. Create New Item B.4 entitled"Pipe Bedding",to provide funds at unit <br /> price of$36.00 per CY at an estimated quantity of 30 CY of"Pipe Bedding", resulting in an increase <br /> of$1,080.00 to the contract. <br /> New Item B.5–Allocation of Previously Incurred Joint Costs. Create New Item B.5 entitled <br /> "Allocation of Previously Incurred Joint Cost",to provide funds at Lump Sum price of$7,049.01 <br /> resulting in an increase of$7,049.01 to the contract. <br /> Exhibit B—Justification: <br /> The work, new items B.1 thru B.5, is Port of Everett directed extra work to remedy an ongoing ti <br /> degradation of a segment of the Port of Everett's storm drainage systems. <br /> In accordance with–Interlocal Agreement between the City of Everett and the Port of Everett <br /> regarding Puget Sound Outfall 6 and Puget Sound Outfall 2, Dated July 3,2014; Section 1 –PSO 6 <br /> Work, H. Cost Sharing,2. Port Additional Work, "The Port will pay 100% of the costs related to the <br /> Port Additional Work". <br /> Exhibit C—Additional Contract Time: <br /> This work will require the addition of 21 calendar days to the contract. <br /> Page 3 of 3 <br />