BID TABULATION Bond Street Site Cleanup W.O.#UP 3356- 6/6/08
<br /> Prepared By:Eugene Houtby
<br /> For:Heather Griffin,Project Engineer 3 Kings PSC Industrial
<br /> Nuprecon, LP Environmental Inc. Plats Plus Inc. Outsourcing LP CCS
<br /> ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
<br /> # ITEM DESCRIPTION UNIT QUAN PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
<br /> 1 Mobilization LS 1 $19,994.75 $19,994.75 $7,782.00 $7,782.00 $18,500.00 $18,500.00 $30,767.80 $30,767.80 $20,846.00 $20,846.00
<br /> 2 Temporary Erosion Control LS 1 $8,616.05 $8,616.05 $5,904.00 $5,904.00 $32,750.00 $32,750.00 $6,293.42 $6,293.42 $7,044.00 $7,044.00
<br /> 3 Street Sweeping Hour 60 $111.68 $6,700.80 $104.55 $6,273.00 $130.00 $7,800.00 $89.00 $5,340.00 $135.50 $8,130.00
<br /> 4 Dewatering LS 1 $5,252.14 $5,252.14 $17,681.00 $17,681.00 $34,500.00 $34,500.00 $9,296.17 $9,296.17 $6,251.00 $6,251.00
<br /> 5 Excavate,Stockpile,Load,and EA 3300 $6.88 $22,704.00 $18.57 $61,281.00 $16.00 $52,800.00 $22.46 $74,118.00 $36.21 $119,493.00
<br /> Haul Contaminated Soil-
<br /> Non-tiazaraous-Rinker
<br /> Materials,Everett
<br /> 6 Excavate,Stockpile,Load,and Tons 100 $96.47 $9,647.00 $125.91 $12,591.00 $132.00 $13,200.00 $89.18 $8,918.00 $110.61 $11,061.00
<br /> Haul Contaminated Soil- Waste Management- Chemwaste Waste Management Waste Management Arlington OR-WM
<br /> Dangerous-Specify Subtitle C Arlington Arlington LF Arlington,OR Landfill
<br /> disposal location with bid.
<br /> 7 Excavate,Stockpile,Load,and Tons 100 $96.47 $9,647.00 $48.41 $4,841.00 $66.00 $6,600.00 $30.68 $3,068.00 $55.17 $5,517.00
<br /> Haul Contaminated Soil-Non- Waste Rebanco Allied Waste- Roosevelt Rabanco
<br /> Hazardous,Lead Greater Than Management- Everett Landfill via
<br /> 250 mg/kg,and Passing TCLP Columbia •Transfer Rabanco
<br /> Requirement. Specify Subtitle D Ridge
<br /> disposal location with bid.
<br /> 8 Dispose Contaminated Soil- Tons 3300 $50.75 $167,475.00 $46.00 $151,800.00 $25.00 $82,500.00 $51.00 $168,300.00 $45.59 $150,447.00
<br /> Non-hazardous Rinker Materials
<br /> •
<br /> 9 Dispose Contaminated Soil- Tons 100 $159.86 $15,986.00 $144.90 $14,490.00 $290.00 $29,000.00 $122.00 $12,200.00 $138.60 $13,860.00
<br /> Dangerous.Specify Subtitle C Waste Chemwaste Waste Waste WM-
<br /> disposal location with bid. Management- Management- Management- Arlington
<br /> Arlington Arlington LF Arlington OR
<br /> OR,Landfill
<br /> 10 Dispose Contaminated Soil- Tons 100 $159.86 $15,986.00 $45.60 $4,560.00 $62.00 $6,200.00 $48.00 $4,800.00 $49.87 $4,987.00
<br /> Non-Hazardous,Lead Greater
<br /> than 250 mg/kg,and Passing Waste Rebanco Allied Waste Roosevelt Rabanco
<br /> TCLP Requirement. Specify Management- Everett Landfill
<br /> Subtitle D disposal location with Columbia Transfer
<br /> bid. Ridge •
<br /> 11 Force Account FA 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00
<br /> 12 Gravel Borrow Tons 3200 $19.34 $61,888.00 $22.20 $71,040.00 $28.00 $89,600.00 $18.00 $57,600.00 $20.84 $66,688.00
<br /> 13 Ballast Tons 300 $24.83 $7,449.00 $29.13 $8,739.00 $40.00 $12,000.00 $23.00 $6,900.00 $70.03 $21,009.00
<br /> Subtotals: $381,345.74 $396,982.00 $415,450.00 $417,601.39 $465,333.00
<br /> 11 Totals WA Sales Tax $32,795.73 $34,140.45 $35,728.70 $35,913.72 $40,018.64
<br /> r Contract Total: $414,141.47 $431,122.45 $451,178.70 $453,515.11 $505,351.64
<br />
|