SECTION 01323 <br />NETWORK ANALYSIS SCHEDULES <br />include activity numbers of the CPM schedule, and be updated [weekly, bi-weekly] to be <br />discussed at the progress meetings. The three-week bar chart field schedule shall be <br />submitted to the Resident Engineer twenty-four (24) hours before the [weekly, bi-weekly] <br />progress meeting. <br />PART 2 — PRODUCTS <br />Not Used <br />PART 3 — EXECUTION <br />1.12 COST -LOADING OF SCHEDULE AND PRODUCTION OF SCHEDULE OF VALUES <br />For each lump sum bid item, the contractor shall cost load all activities in the CPM Progress <br />Schedule that comprise the lump sum bid item such that the total cost of all such cost loaded <br />activities equals the lump sum bid price for the bid item. The schedule of values shall be developed <br />from (linked to) the cost loaded CPM Progress Schedule. The CPM Progress Schedule, cost - <br />loaded for the activities comprising lump sum bid items, and the schedule of values shall be <br />prepared, submitted, approved, maintained, and updated as specified. The monthly updated cost <br />loaded CPM Progress Schedule will be the basis for progress measurement for each activity in the <br />schedule of values. <br />END OF SECTION 01323 <br />Capital Projects Commuter Rail 01323-9 IFB No. RTAICP 21-06 <br />Everett Station Phase 2 NETWORK ANALYSIS SCHEDULES <br />