SP-1.05 ORDER OF PRECEDENCE <br />Section 1.05 of the General Provisions is modified as follows: <br />.eplace Section 1.05, Order of Precedence, with the following: <br />A. The Contract Documents are intended to be complimentary and to describe and <br />provide for a compiete Work. They are also interpreted in harmony so as to <br />avoid conflict, with words and phrases interpreted consistent with construction <br />and design industry standards. The Contract Documents identified below are <br />listed in order of precedence. To the extent that there are different provisions in <br />Contract Documents that address the same matter or subject and these different <br />provisions conflict, the document having the highest priority that addresses the <br />r�atter or subject shall control. If conflicting provisions within the same level of <br />Contract Documents exist, and one is more stringent than another, the more <br />stringent provision will prevail. <br />Change Orders <br />Agreement Form with Attachment(s) <br />Special Provisions <br />General Provisions <br />Contract Specifications <br />City of Everett Design and Construction Standards and Specifications <br />2006 State of Washington Standard Specifications for Road, Bridge and <br />Municipal Construction <br />Contract Drawings <br />City of Everett Standard Drawings <br />2006 State of Washington Standard Plans for Ro�d, Bridge and Municipal <br />Construction <br />Labor Compliance Manual <br />Utility Standards <br />Industry Standards, when identified as being Contract Documents <br />B. In case of differences between smail and large-scale drawings, the large-scale <br />drawings shall govern. Schedules on drawings shall take precedence over <br />conflicting notations on drawings. In the event of discrepancy between any <br />drawing and the figures written thereon, the figures, unless otherwise indicated, <br />shall govern over scaled dimensions. <br />C. Utility Standards referenced in the Contract Documents shall apply only to <br />material and workmanship with respect to work, which upon completion is to be <br />accepted by a municipality or a utility company. The commercial terms within <br />these references (e.g. Control of Work, Temporary Traffic Control, Legal <br />Capital Projecls Commuter Rail Special Provisions IFB No. P.TA/CP 21-06 <br />� Everetl Slation Phase 2 Section 00300 Page 1 Addendum No. 4 <br />