• <br /> Project: WFP Clearwell No. 2 <br /> Change Order No.6 <br /> Effective August 24, 2009 <br /> Contractor and City agree as follows: <br /> Change Order#6 adds "Bid Item#9—Change Order#6" in the amount of$169,938.38. The scope of <br /> Work shall be changed to the extent described in Exhibit A. <br /> 1. In full and complete compensation for the changes described in Exhibit A,including all direct <br /> and indirect costs and impacts, the contract price shall be adjusted as described in this Change <br /> Order. <br /> 2. The duration of the Contract shall be adjusted to the extent described in this Change Order. <br /> 3. Contractor waives and releases any and all claims arising out of, or related to, this Change <br /> Order, the work described in Exhibit A, and all work and actual or constructive changes that <br /> occurred or began prior to the date of this Change Order, including,but not limited to, claims <br /> for equitable adjustment of time and compensation, delay, impact,overhead, or inefficiencies. <br /> This provision does not apply to requests for equitable adjustment of time or price for which <br /> the Contractor timely and properly provided notice of a differing site condition, protest, <br /> dispute, claim or Contract Claim as required by the Contract Documents. If the Contract <br /> Documents establish a time period for notice of a differing site condition,protest, dispute, <br /> claim, or Contract Claim that ends after the date of this Change Order,but relates to work <br /> performed prior to the date of this Change Order, then this provision does not apply if the <br /> Contractor timely and properly submits such notice <br /> 4. This Change Order only changes the contract between Contractor and City to the extent <br /> explicitly provided herein. <br /> a C • <br /> h x <br /> Attest: Approved As to Form: <br /> Mayor City Clerk City Attorney <br /> Date: Date: Date: <br /> Recommended By: <br /> Construction Project Engineer (if Engineering Department Director <br /> Manager(if applicable) Manager(if <br /> applicable) applicable) <br /> ce721.7%Add-- <br /> / Date: Date: ��L <br /> -07 <br /> Date: ''/ h/a 9 Date: '1.1N)a� <br /> Y F b CONTRACTOR r ; <br /> By /I / Date: 6- Iy -07 <br /> Officer <br /> Page2of4 22 <br />