durations for all activities. Contractor shall not attempt to "grab the Float" or make any <br /> effort to use any Float in the Progress Schedule for the benefit of the Contractor. <br /> g. Contractor shall submit with each Application for Payment or progress pay estimate an <br /> updated Progress Schedule,but no less often than monthly. If requested by the Owner's <br /> Representative or the Owner, Contractor shall prepare and submit updated Progress <br /> Schedules from time to time,which may be more frequent than monthly. <br /> h. The Contractor hereby expressly agrees and acknowledges that any failure by <br /> Contractor to provide accurate, complete, current and updated schedules with each and <br /> every progress pay estimate or Application for Payment constitutes a waiver of any and <br /> all claims or requests for adjustment of Contract Sum or Time that arise out of, result <br /> from, or are caused by, any Delay on the Project or scheduling of the Work. Timely <br /> submission of monthly updated schedules is a condition precedent to any later or <br /> subsequent Contract Claim or request for an adjustment of either Contract Sum or Time <br /> related to or arising out of time, an alleged Delay, or the schedule or sequence of Work. <br /> Similarly, the parties agree the Owner may withhold progress pay estimates if updated <br /> schedules are not timely submitted. These remedies are cumulative and not exclusive <br /> of any other remedy. The Owner's use of one or more of these remedies does not <br /> constitute an election or prevent the Owner from pursuing other remedies for this or <br /> other defaults. <br /> i. The Owner's Representative's review of any schedule shall not transfer any of the <br /> Contractor's responsibilities to the Owner. The Contractor alone shall remain <br /> responsible for adjusting forces, equipment, and work schedules to ensure completion <br /> of the Work within the Contract Time. Review by the Owner or Owner's <br /> Representative shall not constitute approval or acceptance of the Contractor's <br /> construction means, methods, sequencing, logic, order, precedence and succession of <br /> activities or Contractor's ability to complete the Work in a timely manner. Any <br /> mistakes or errors in any schedule, including, but not limited to, mistakes or errors of <br /> logic, order, precedence, and duration, are and remain the Contractor's. The Owner or <br /> Owner's Representative may comment upon the schedule. <br /> C. Extensions of Contract Time <br /> 1. Any requests for extensions in Contract Time, whether resulting from Extra Work directed <br /> by the Owner or not, shall be accompanied by an analysis of schedules using the critical path <br /> method. This analysis shall include an updated schedule, an as-planned schedule, an as-built <br /> schedule, a but-for schedule, and narrative explaining the alleged causes, schedule impacts <br /> and all costs related to or arising out of the proposed extension. Any requests for extensions <br /> of Contract Time by the Contractor shall be submitted in accordance with these General <br /> Conditions. Extensions of Contract Time will be granted only as provided in the General <br /> Conditions and to the extent that affected critical activities exceed the Total Float time along <br /> the affected paths of the reviewed Preliminary Schedule at the time the change was <br /> authorized in writing by the Owner. Contractor has the burden of clearly and convincingly <br /> demonstrating entitlement to any adjustment of Contract Time. <br /> 2. If the Owner is solely responsible for any Delay to Substantial Completion, Physical <br /> Completion, Completion Date, or Final Acceptance, the Contractor shall only be entitled to <br /> compensation or other damages as described in 12.4 Remedies, provided that Contractor <br /> timely gave Notice pursuant to ARTICLE 10. NOTICE TO OWNER, timely submitted a <br /> Contract Claim pursuant to ARTICLE 12. CONTRACT CLAIMS and fulfilled the <br /> requirements of 5.B. Construction Schedule. <br /> D. Construction Progress <br /> WFP Operations Building Seismic Retrofit-Rebid January 6, 2017 <br /> WO#UP3600 007213 -23 <br />