1. The Contractor shall furnish all labor, materials, facilities and Equipment necessary to insure <br /> the prosecution and completion of the Project within the interim milestones, Substantial <br /> Completion, Physical Completion and Completion Dates of the Contract. If Work falls <br /> seven (7) days or more behind the reviewed Preliminary Schedule, the Contractor agrees <br /> that, at its sole cost and expense, it will take all actions necessary to return the Project to the <br /> accepted schedule. These actions may include the following: <br /> a. Increase labor in quantities and crafts. <br /> b. Increase the number of working hours per shift, shifts per working day, working days <br /> per week, or the amount of Equipment, or any combination of the foregoing. <br /> c. Reschedule activities. <br /> 2. If requested by the Owner's Representative, the Contractor shall prepare a proposed <br /> schedule revision demonstrating a plan to make up the lag in progress and insure completion <br /> of the Work within the Contract Time. All actions taken to return the Project to the accepted <br /> schedule are at the Contractor's expense. <br /> 3. The Contractor shall pay all costs incurred by the Owner that result from the Contractor's <br /> action to return the Project to its accepted schedule, including, but not limited to, additional, <br /> overtime, or third party inspection, design and construction management service costs. <br /> Contractor agrees that Owner shall deduct such charges from payments due the Contractor. <br /> It is further understood and agreed that none of the services performed by the Owner's <br /> Representative in monitoring, reviewing and reporting Project status and progress shall <br /> relieve the Contractor of responsibility for planning and managing construction Work in <br /> conformance with the construction schedule. <br /> E. Delays <br /> 1. General <br /> a. In the event of a Delay,the Contractor shall take immediate steps to minimize the Delay <br /> or avoid further Delay. The Contractor agrees it shall not make any Contract Claim or <br /> request for adjustment of Contract Time or Contract Sum based upon Delays for which <br /> it did not timely provide Notice to the Owner. <br /> 2. Bonuses <br /> a. If the Contract Documents provide the Contractor with a bonus or other incentive for <br /> early completion of a milestone or other completion point, Contractor assumes the risk <br /> of Delays caused wholly or partially by third parties. Owner shall not pay any bonus <br /> that Contractor would have achieved but for any and all Delays caused in whole or in <br /> part by a third party. By way of example only, the Contractor bears the risk of utility <br /> companies' failure to locate underground utilities accurately and the Contractor bears <br /> the risk of timely asking for the marking of the location of underground utilities. <br /> 5.3 Suspension Procedures <br /> A. The Owner may, at its convenience and at any time and without cause, suspend all or any part of <br /> the Work by notice in writing to the Contractor. The Work shall be resumed by the Contractor <br /> within five (5) days after receiving written notice from the Owner to do so. The Contractor will <br /> be allowed an increase in the Contract Sum or an extension of Contract Time, or both, directly <br /> attributable to any suspension in accordance with the Change Order procedures herein; provided, <br /> the Contractor shall not be entitled to an increase to the extent caused by the Contractor. <br /> WFP Operations Building Seismic Retrofit-Rebid January 6, 2017 <br /> WO#UP3600 007213 -24 <br />