The Substantial Completion date of the entire or a portion of the Project will be established as the <br /> date when the Owner actually begins using the Project or portion of the Project for its intended <br /> purpose. Division of responsibilities between Owner and Contractor, beginning of warranties, <br /> and any other issues relating to Substantial Completion shall be as specified in 5.7. Substantial <br /> Completion. <br /> 5.7 Substantial Completion <br /> A. When the Contractor considers the Work to be Substantially Complete and ready for its intended <br /> use, it shall give Notice to the Owner's Representative. The Notice shall include an itemized list <br /> of remaining incomplete Work. If the Owner's Representative determine the Work is not <br /> substantially complete, the Contractor will be notified in writing, identifying the reasons for such <br /> a determination. <br /> 1. If the Owner's Representatives find the Work substantially complete, he or she will meet <br /> with the Contractor to: <br /> a. Prepare a Punch List of incomplete items of Work. <br /> b. Define the division of responsibility between Owner and Contractor with respect to <br /> security, operation,maintenance,heat,utilities, insurance, and warranties. <br /> c. Describe any other issues related to acceptance of the substantially completed Work. <br /> B. If the Owner's Representative is not an employee of the Owner, the Owner's Representative will <br /> write to the Owner upon reaching agreement with the Contractor, certifying that the Work is <br /> substantially complete, listing the items of incomplete Work, stating the date for completion of <br /> incomplete Work, defining the division of responsibilities, and setting forth any other terms <br /> related to acceptance. In such event, the Owner will review the Owner's Representative's <br /> certification that the Work is substantially complete. If the Owner concurs,the Owner will notify <br /> the Contractor in writing that the Work is accepted as substantially complete. Except for any <br /> portion(s) of Work specified for early completion or required by the Owner for early possession, <br /> Substantial Completion will not occur for any Work until the entire Project is ready for <br /> possession and use. The acceptance notice will include a Punch List of incomplete Work items <br /> and corrective Work, set the date for their completion and repair, describe the division of <br /> responsibility between the Owner and Contractor, and describe any other terms of acceptance. <br /> The Contractor will acknowledge receipt of the acceptance notice in writing, indicating <br /> acceptance of all of its terms and provisions. <br /> C. Subsequent to the Substantial Completion date, the Owner may exclude the Contractor from the <br /> Work during such periods when construction activities might interfere with the intended <br /> operation of the Project. The Owner, however, shall allow the Contractor reasonable access for <br /> completion or correction of incomplete Punch List items. <br /> 5.8 Acceptance of Work <br /> A. Upon completion of the Project, including, but not limited to,record drawings, as-builts,required <br /> reports and operations and maintenance manuals, the Contractor shall so notify the Owner's <br /> Representative in writing. Upon receipt of the notification, the Owner's Representative will <br /> promptly, by personal inspection, determine the actual status of the Work in accordance with the <br /> terms of the Contract. If the Owner's Representative finds materials, Equipment, or <br /> workmanship that do not meet the terms of the Contract, he or she will prepare a Punch List of <br /> such items and submit it to the Contractor. Following completion of the corrective Work by the <br /> Contractor, the Owner's Representative will notify the Owner that the Work has been completed <br /> WFP Operations Building Seismic Retrofit-Rebid January 6,2017 <br /> WO#UP3600 007213 -28 <br />