i II <br /> CITY OF EVERETT PUBLIC WORKS <br /> SPECIAL PROVISIONS <br /> F. Float: The measure of leeway in starting and completing an activity. <br /> 1. Float time belongs to the Owner. <br /> 2. Free float is the amount of time an activity can be delayed without adversely affecting the <br /> early start of the successor activity. <br /> 3. Total float is the measure of leeway in starting or completing an activity without <br /> adversely affecting the planned Project completion date. <br /> G. Fragment: A partial or fragmentary network that breaks down activities into smaller activities <br /> for greater detail <br /> H. Major Area: A story of construction, a separate building, or a similar significant construction <br /> element. <br /> I. Milestone: A key or critical point in time for reference or measurement. <br /> J. Network Diagram: A graphic diagram of a network schedule, showing activities and activity <br /> relationships. <br /> K. Resource Loading: The allocation of manpower and equipment necessary for the completion of <br /> an activity as schedule. <br /> 1.4 INFORMATIONAL SUBMITTALS <br /> A. Qualification Data: For Contractor's scheduling personal or Contractor's scheduling Consultant. <br /> B. Submittals Schedule: Submit three hard copies of the schedule and an electronic copy in PDF <br /> format. Arrange the following information in a tabular format: <br /> 1. Scheduled date for first submittal. <br /> 2. Specification Section number and title. <br /> 3. Submittal category(action or informational). <br /> 4. Name of subcontractor. <br /> 5. Description of the work covered. <br /> 6. Scheduled date for Engineer's and Owner's final release or approval. <br /> C. Preliminary Construction Schedule: Submit two hard copies and an electronic copy in PDF <br /> format. <br /> 1. Approval of cost-loaded preliminary construction schedule will not constitute approval of <br /> Schedule of Values for cost-loaded activities. <br /> D. Preliminary Network Diagram: Submit two hard copies and an electronic copy in PDF format, <br /> large enough to show entire network for entire construction period. Show logic ties for <br /> activities. <br /> E. Contractor's Construction Schedule: Submit two opaque copies of initial schedule, large enough <br /> to show entire schedule for entire construction period. <br /> WFP Operations Building Seismic Retrofit-Rebid January 6,2017 <br /> WO#UP3600 013200-2 <br />