My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2009/12/09 Council Agenda Packet
>
Council Agenda Packets
>
2009
>
2009/12/09 Council Agenda Packet
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
4/12/2017 8:46:53 AM
Creation date
4/12/2017 8:46:22 AM
Metadata
Fields
Template:
Council Agenda Packet
Date
12/9/2009
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
124
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Increased Oversight and Assistance to Contractor <br /> In the course of the project the members of the design and construction <br /> management team have found the level of effort necessary to answer contractor <br /> questions and review submitted materials has exceeded what would normally be <br /> expected for a project of this nature. The team has endeavored to be as <br /> responsive and timely as possible as all are aware of the tight schedule and <br /> critical deadline that this project faces. In addition, a number of the companies <br /> supporting the construction have felt that additional effort has been expended to <br /> guide the contractor through the construction, answering questions and providing <br /> solutions to construction issues that would normally be handled by the contractor. <br /> If the November 29th 2009 BRT opening date was not critical a less contractor <br /> supportive management approach would have been utilized which would have <br /> resulted in additional submittals rejected for not meeting contract specification <br /> requirements, basic spec book requirements and the project schedule would <br /> have slipped well past November 29th 2009. <br /> Some of the efforts beyond what was anticipated include: <br /> We are currently at RFI tt'16 with a significant portion of the construction still to be <br /> completed. While RFIs are part of construction, the quantity and nature of the <br /> RFIs on this project have been required greater effort than anticipated. A number <br /> of the questions asked have required a significant amount of redesign work on <br /> the design team's part. The majority of the design changes were due either to <br /> unknown site conditions (shallow electrical conduits), accommodating contractor <br /> phasing (redesign of the integral platform curbs so the platform could be <br /> constructed first), or contractor misunderstandings (catch basin collar.) <br /> Numerous material submittals, especially crushed aggregate materials, have <br /> been unacceptable per the specifications and required resubmittal. Each time a <br /> material is submitted the design time must review the submittal and in the case of <br /> soil, aggregate, and paving materials lab work performed on the submittal. <br /> Submittals that must be resubmitted require this work to be performed multiple <br /> times. <br /> The method in which Corstone has organized their construction has required that <br /> the HWA testing be onsite to perform testing far more than they had anticipated <br /> based on typical project organization. As an example HWA had assumed that <br /> the concrete paving for the project would be made in two pours, requiring 2 days <br /> of onsite observation. It currently appears that there will be at least 5 separate <br /> pours, requiring 5 days of onsite observation and additional samples and lab <br /> work. <br /> In order to accommodate the phasing and accelerated project schedule <br /> additional concrete cylinders have been collected in order to determine early <br /> concrete strength, something that is not typically done. <br /> 48 <br />
The URL can be used to link to this page
Your browser does not support the video tag.