BID TABULATION •
<br /> Lift Station 5 Force Main
<br /> w.o.#UP 3'to0
<br /> Dale 12/9/2009
<br /> 1 'repared By:William Barret[
<br /> ••For:Heather Griffin,Project Engineer ENGINEER'S ESTIMATE Buno Construction SRV Construction McClure&Sons Durnford&Sons
<br /> ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
<br /> 6 ITEM DESCRIPTION UNIT •UANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
<br /> 1 Mobilization LS I $40,000.00 $40,000.00 $20,000.00 $20,000.00 $28,750.00 $28,750.00 $3,600.00 $3,600.00 $20,000.00 $20,000.00
<br /> 2 Traffic Control Labor Hours 100 $75.00 $7,500.00 $44.00 $4,400.00 $50.40 $5,040.00 $56.00 $5,600.00 - $65.00 $6,500.00
<br /> 3 Maintenance&Protection of LS 1 $7,500.00 $7,500.00 $4,000.00 $4,000.00 '$5,500.00 $5,500.00 $4,000.00 $4,000.00 $1,000,00 $1,000.00
<br /> Traffic Control
<br /> 4 Sawcutting Pavement,Final Joint LF 400 $5.00 $2,000.00 $4.00 $1,600.00 $2.80 $1,120.00 $5.00 $2,000.00 $2.00 $800.00
<br /> Cut,Up to 6-Inch Thickness
<br /> 5 Sawcutting Pavement,Final Joint LF 400 $0.75 $300.00 $0.50 $200.00 $3.15 $1,260.00 $6.00 $2,400.00 $4.00 $1,600.00
<br /> Cut,Additional 1-Inch Thickness
<br /> 6 Street Cleaning and Sweeping LS 1 $3,000.00 $3,000.00 $800.00 $800.00 $4,100.00 $4,100.00 $3,000.00 $3,000.00 $3,000.00 $3,000.00
<br /> 7 Control Density Fill CY 100 $150.00 $15,000.00 $90.00 $9,000.00 $120.00 $12,000.00 $136.00 $13,600.00 $100.00 $10,000.00
<br /> 8 HMA Class 1/2"PG 64-22 Ton 30 $150.00 $4,500.00 $118.00 $3,540.00 $155.60 $4,668.00 $200.00 $6,000.00 $175.00 55,250.00
<br /> 9 Asphalt Treated Base Ton 60 $120.00 $7,200.00 $118.00 $7,080.00 $148.60 $8,916.00 $200.00 $12,000.00 $175.00 $10,500.00
<br /> 10 Pavement Patch,Temporary Ton 100 $200.00 $20,000.00 $80.00 $8,000.00 $115.00 $11,500.00 $200;00 $20,000.00 $125.00 $12,500.00
<br /> }L Trench Excavation Safety System LS 1 $20,000.00 $20,000.00 $5,000.00 $5,000.00 $0.10 $0.10 S3,000.0.0 $3,000.00 $3,500.00 53,500.00
<br /> 12 Surveying LS 1 $5,000.00 $5,000,00 $1,500.00 $1,500.00 $1,400.00 $1,400.00 $3,000.00 $3,000.00 $2,000.00 $2,000.00
<br /> 13 Utility Potholing LS 1 $20,000.00 $20,000.00 $1,500.00 $1,500.00 $3,000.00 $3,000.00 $3,000.00 $3,000.00 $8,000.00 $8,000.00
<br /> 14 Combined Sewer Force Main,8- LF 450 $250.00 $112,500.00 $200.00 $90,000.00 $136.80 $61,560.00 $162.00 $72,900.00 $180.00 $81,000,00
<br /> Inch Diameter
<br /> 15 8-Inch Flexible Expansion Joint LS 1 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,750.00 $5,750.00 $5,000.00 $5,000.00 $10,000.00 $10,000.00
<br /> 16 Lift Station 5 Valves and Piping LS 1 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $39,900.00 $39,900.00 $56,000.00 $56,000.00 $35,000.00 $35,000.00
<br /> 17 Pipe Supports LS I $10,000.00 $10,000.00 $6,000.00 $6,000.00 $12,850.00 $12,850.00 $24,000.00 $24,000.00 $20,000.00 $20,000.00
<br /> 18 Pipe Insulation LS 1 $7,500.00 - $7,500.00 $8,000.00 $8,000.00 $14,000.00 $14,000.00 $6,000.00 $6,000.00 $20,000.00 $20,000.00
<br />
|