BID TABULATION
<br /> Lift Station 5 Force Main
<br /> W.O.#UP 3#00 r.....
<br /> Date 12/9/2009
<br /> Prepared By:William Barrett
<br /> •For:Heather Griffin,Project Engineer ENGINEER'S ESTIMATE Mosbrucker Construction ICI Construction Strider Construction Thomco Construction
<br /> ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
<br /> 8 ITEM DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
<br /> 19 72-Inch Manhole LS 1 $15,000.00 $15,000.00 $7,500.00 $7,500.00 $19,500.00 $19,500.00 $9,500.00 $9,500.00 $10,500.00 $10,500.00
<br /> 20' Temporary Sedimentation& LS 1 $5,000.00 $5,000.00 $1,500.00 $1,500.00 $3,500.00 $3,500.00 $700.00 $700.00 $1,810.00 $1,810.00
<br /> Erosion Control
<br /> 21 Crushed Surfacing Top Course Ton 100 $40.00 $4,000.00 $22.00 $2,200.00 $34.00 $3,400.00 $50.00 $5,000.00 $22.27 $2,227.00
<br /> 22 Crushed Surfacing Base Course. Ton 475 $45.00 $21,375.00 $22.00 $10,450.00 $23.00 $10,925.00 $19.00 $9,025.00 $20.73 $9,846.75
<br /> 23 Gravel Borrow Ton 500 $30.00 $15,000.00 $18.00 $9,000.00 $19.00 $9,500.00 $15.00 $7,500.00 $17.60 $8,800.00
<br /> 24 Foundation Material Class A Ton 20 $50.00 $1,000.00 $40.00 $800.00 $40.00 $800.00 $19.00 $380.00 $50.00 $1,000.00
<br /> 25 Concrete Sidewalk SY 120 $200.00 $24,000.00 $50.00 $6,000.00 $44.00 $5,280.00 $40.00 $4,800.00 $36.39 $4,366.80
<br /> 26 Concrete Curb LF 200 $100.00 $20,000.00 $30.00 $6,000.00 $26.00 $5,200.00 $30.00 $6,000.00 $26.26 $5,252.00
<br /> 27 Curb Ramp EA 1 $2,000.00 $2,000.00 $1,200.00 $1,200.00 $1,200.00 $1,200.00 $1,250.00 $1,250.00 $1,473.00 $1,473.00
<br /> 28 Force Account Work FA 1 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00
<br /> G
<br /> Subtotals: $469,375.00 $267,550.00 $274,450.00 $276,325.00 $282,372.27
<br /> WA Sales Tax;9.2% $43,182.50 $24,614.60 $25,249.40 $25,421.90 $25,978.25
<br /> Contract Totals: $512,557.50 $292,164.60 $299,699.40 $301,746.90 $308,350.52