BID TABULATION
<br /> Lift Station 5 Force Main
<br /> W.O.#UP 5400 ......
<br /> Date 12/9/2009
<br /> •
<br /> `Trepared By:William Barrett
<br /> For:Heather Griffin,Project Engineer ENGINEER'S ESTIMATE R.L.Alia Construct Company Wiseman Utilities B&L Utility
<br /> ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
<br /> 6 ITEM DESCRIPTION UNIT quANTrrt PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
<br /> 19 72-Inch Manhole LS -1 $15,000.00 , $15,000.00 l $20,000.00 $20,000.00 $9,000.00 $9,000.00 $35,800.00 $35,800.00 $7,600.00 $7,600.00
<br /> 20 Temporary Sedimentation& LS 1 $5,000.00 $5,000.00 $1,000.00 $1,000.00 $2,000.00 $2,000.00 $3,000.00 $3,000.00 $1,500.00 $1,500.00
<br /> Erosion Control
<br /> 21. Crushed Surfacing Top Course Ton 100 $40.00 $4,000.00 $20.00 $2,000.00 $11.70 $1,170.00 $23.00 $2,300.00 $1.00 $100.00
<br /> 22 Crushed Surfacing Base Course Ton 475 545.00 $21,375.00 $20.00 $9,500.00 $11.70 $5,557.50 $23.00 $10,925.00 $1.00 $475.00
<br /> 23 Gravel Borrow Ton 500 $30.00 $15,000.00 $0.10 $50.00 $8.75 $4,375.00 $20.00 $10,000.00 $1.00 $500.00
<br /> 24 Foundation Material Class A Ton 20 S50.00 $1,000.00 $5.00 $100.00 $11.70 $234.00 S23.00 $460.00 $5.00 $100.00
<br /> 25 Concrete Sidewalk SY 120 $200.00 $24,000.00 $40.00 $4,800.00 $50.00. $6,000.00 S59.00 $7,080.00 $40.00 $4,800.00
<br /> 26 Concrete Curb LF 200 $100.00 $20,000.00. $20.00 $4,000.00 $32.00 $6,400.00 $33.00 $6,600.00 $40.00 $8,000.00
<br /> 27 Curb Ramp EA 1 $2,000.00 $2,000.00 $1,200.00 $1,200.00 $2,000.00 $2,000.00 $1,650.00 $1,650.00 $2,000.00 $2,000.00
<br /> 28 Force Account Work FA 1 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00
<br /> Subtotals: $469,375.00 $357,437.50 $362,186.50 $403,545.00 $435,475.00
<br /> WA Sales Tax:9.2% $43,182.50 $32,884.25 $33,321.16 $37,126.14 $40,063.70 -
<br /> Contract Totals: $512,557.50 $390,321.75 $395,507.66 $440,671.14 $475,538.70 p