12
<br /> agency comments, soils information data gathered from field exploration, and hydrological
<br /> information provided by other team members. Task includes demolition, erosion control,
<br /> preload, construction phasing and/or stream diversion/dewatering, layout, grading and
<br /> drainage, (1) bridge, footing, and approaches in Railroad Corridor, (1) bridge, footing, and
<br /> approaches at Bigelow Creek crossing to support pedestrian/bicycle/light maintenance
<br /> access, (1) memoranda for future use by CITY and Developer addressing requirements to
<br /> upgrade the bridge, footing, and approaches at Bigelow Creek crossing to support fire truck
<br /> access, planting, and detail design; Special Provisions; Summary of Quantities and cost
<br /> estimate; in the following submittal packages:
<br /> a. 60% PS&E for Early Phase Projects
<br /> b. 100% PS&E for Basic Trail and Enhanced Drainage Channel in Railroad Corridor
<br /> c. 60% PS&E for South Wetland Complex and Stormwater Management
<br /> Implementation (Bigelow Creek)
<br /> 8.2 Utility Design Coordination: Incorporate plans, specifications and supporting
<br /> documentation, as prepared by Group 2, for design of utilities in Railroad Corridor. Utilities
<br /> to include sanitary force main located longitudinally along corridor, and storm drainage
<br /> features located west of, and extending to east of, the proposed trail. Project length for trail
<br /> and utilities to extend from 41st Street to 3 Acre Park; project length for enhanced drainage
<br /> swale to extend from 41st Street to outfall at Snohomish River; project length for surface
<br /> drainage to extend from Snohomish outfall to 3 Acre Park. Incorporate utilities into layout
<br /> and grading plans by reference; include utility plans and details as prepared by Group 2 into
<br /> plan set; include special provisions, cost estimate, and supporting engineering
<br /> documentation as necessary for permit approval as prepared by Group 2 into final
<br /> deliverable package. Coordinate with Group 2 to verify combined facilities satisfy CITY
<br /> objectives and permit conditions.
<br /> Deliverables: 1) 60% PS&E for three projects; 2) 90% PS&E for one project; 3) 100% PS&E
<br /> for one project; 4) Memoranda addressing final design requirements for structure design to
<br /> support fire truck access.
<br /> 009. 3-Acre Park Development
<br /> 9.1 3-Acre Park Design: Advance design and detailing of park and park components,
<br /> incorporating information made available through CITY review and any preliminary permit
<br /> agency comments, soils information data gathered from field exploration, and hydrological
<br /> information provided by other team members. Components of the 3-Acre Park include the
<br /> restroom/picnic shelter building, crane refurbishment and (optional) tensile fabric structure,
<br /> crane pad/viewpoint, gangway/ramp and floating dock, including piling support,
<br /> interconnecting trails, parking lot including ingress/egress, access to Lift Station 33 and
<br /> related support facilities, children's play area, interpretive signage. Task includes
<br /> demolition, erosion control, preload (restroom building and lift station 33), layout, grading
<br /> and drainage, restroom building design, lighting and electrical design for the restroom
<br /> building and crane, lighting and electrical design for the parking lot and trails, gangway and
<br /> float design, planting, and detail design; Special Provisions; Summary of Quantities and cost
<br /> estimate; in the following submittal packages:
<br /> a. 60% PS&E for Early Phase Projects
<br /> Deliverables: 1) 60% PS&E for 3-Acre Park.
<br /> 010. Contingency and Misc. Projects/Tasks
<br /> 8
<br /> 74