5 City of Everett 1 March 12,2012 Page 9
<br /> 2012, with down time associated with holidays. We assume periodic interim reports (via phone or email)
<br /> and monthly progress reports associated with invoicing.
<br /> PROJECT BUDGET AND SCHEDULE
<br /> This project budget represents our knowledge of the work already completed, best understanding of the
<br /> requested project elements, and accompanying assumptions. We are in a position to begin after
<br /> receiving your authorization to proceed. We propose to complete our services on a time-and-expense
<br /> basis in accordance with the attached Schedule of Charges. For the scope of services described above,
<br /> we estimate that our fee will be not exceed $165,000. This budget estimate is made based on the scope
<br /> of services and expected deliverable schedule broken out per task below in Table 1.
<br /> TABLE 1. PROJECT SCOPE OF SERVICES,BUDGET ESTIMATE AND SCHEDULE
<br /> TASK DESCRIPTION • Begin date: End date ESTIMATED FEES
<br /> Task 1- Data Collection and Kickoff March 19,2012 March 26,2012 ' $ 5,921
<br /> Task 2 -Geomorphic Assessment March 26,2012 April 16,2012 $ 16,394
<br /> Task 3 -Slope Stability Assessment April 2,2012 April 30,2012 $ 8,224 •
<br /> Task 4- Hydrology and Hydraulics April 2,2012 April 30,2012 $ 14,466
<br /> Task 5 - Design Development April,2012 July,2012 $ 74,975
<br /> Alternatives Development April 16,2012 April 30,2012 -
<br /> 30 percent Design April 30,2012 May 21,2012 -
<br /> 90 percent Design May 28,2012 June 18,2012 -
<br /> Bid Documents June 25,2012 July 2,2012 - •
<br /> Task 6 - Permitting Support May,2012 July,2012 $ 5,731
<br /> Task 7 -Services During Construction July,2012 September,2012 $ 29,041
<br /> Bidding Support July, 2012 . • July,2012 -
<br /> Construction Observation and Office August,2012 September,2012 -
<br /> Support
<br /> Task 8- Project Management March,2012 September,2012 $ 10,249
<br /> TOTAL BUDGET $ 165,001
<br /> Services will be provided on a time and materials basis in accordance with the term, conditions, and rates
<br /> set forth in the existing contract between the City of Everett and GeoEngineers dated June 28, 2010.
<br /> GEOENGINEERSij
<br /> File No.0661-086-02
<br /> U