Laserfiche WebLink
7 <br /> Project: WPCF Phase B-2 <br /> Change Order No.5 <br /> Change Order Effective Date: April 9, 2012 <br /> Schedule B Work: <br /> Commencement and Substantial Completion of schedule B work Section 2 (b) of Change Order# 1 <br /> is deleted and replaced with the following: <br /> lithe City for any reason does not deliver to the Contractor the Schedule B Notice to Proceed before <br /> April 18, 2011, then the Contractor shall start on-site Schedule B Work no earlier than March 7, 2012, <br /> and shall substantially complete the Schedule B Work no later than September 15, 2012. <br /> 73 <br />