I <br /> Each working day shall be charged to the Contract as it occurs,beginning on the effective I <br /> date of the Notice to Proceed, unless otherwise provided in the Contract Documents,until <br /> the Contract Work is physically complete. Each week the Engineer will provide the <br /> Contractor a statement that shows the number of working days: (1) charged to the <br /> Contract the week before; (2) specified for the physical completion of the Contract; and <br /> (3) remaining for the physical completion of the Contract. The statement will also show <br /> the nonworking days and partial or whole day the Engineer declares as unworkable. <br /> Within 14 calendar days after the date of each statement, the Contractor shall file a <br /> written protest of any alleged discrepancies in it. To be considered by the Engineer, the <br /> protest shall be in sufficient detail to enable the Engineer to ascertain the basis and <br /> I <br /> I <br /> t <br /> I <br /> r <br /> I <br /> I <br /> I <br /> t <br /> 1 <br /> I <br /> 1 <br /> STREET REGULATOR February, <br /> HAYES 2017 <br /> AND CSO CONTROLS (SRO1, SRO2, AND SRO3) <br /> WO No—UP3398-31 SP— 107a <br />