I <br /> the Work then completed and the materials and Equipment then delivered to the site of the <br /> Work and to leave the Work in a safe and useful condition.Payment for this Extra Work will be <br /> made in accordance with 1-09.4 EQUITABLE ADJUSTMENT. <br /> 1-08.10(8) Ownership of Materials upon Termination <br /> (******) <br /> As of the termination date, whether effected by the City or Contractor as provided herein, all <br /> the Contractor's right, title, and interest in and to materials ordered by the Contractor prior to <br /> termination,whether or not they have been delivered to the site of Work, shall be vested in the <br /> City, and the Contractor shall, upon demand of the City, execute and deliver to the City all <br /> requisite bills of sale, assignments, and other documents of transfer that may be necessary to <br /> give effect to the intention of the termination procedures set forth above. <br /> 1-08.10(9) Opportunity to Cure <br /> (******) <br /> If the Contractor has not already had an opportunity to cure the default or breach the City shall <br /> specify the default or breach and a reasonable period of time to allow the Contractor to cure the <br /> default or breach. The Notice of termination will state the time period in which cure is <br /> permitted and other conditions as the City, in its sole judgment, shall deem appropriate. If <br /> Contractor fails to remedy the breach or default or any of the terms, covenants,or conditions of <br /> this Contract to the City's satisfaction within the time period specified or the City shall have the <br /> right to terminate the Contract without any further obligation to the Contractor. Any such <br /> termination for default shall not in any way operate to preclude the City from also pursuing all <br /> available remedies against Contractor and its sureties for said breach or default. <br /> 1-08.10(10) Waiver of Remedies for Any Breach 111 <br /> (******) <br /> In the event that the City elects to waive its remedies for any breach by Contractor or any <br /> covenant, term or condition of this Contract, such waiver by the City shall not limit the City's <br /> remedies for any succeeding breach of that or of any other term covenant, or condition of this <br /> Contract. <br /> 1-08.10(11) Possession and Use of Completed Portions of the Work <br /> (******) <br /> The City shall have the right to take possession of and use completed or partially completed <br /> portions of the Work even though the time for completing the Work for such portions may not <br /> have expired. Operations and maintenance costs of use of such work will be borne by the City. <br /> Such possession and use shall not be deemed as acceptance of the Work. If such prior <br /> possession or use increases the cost of the Work,the Contractor may be entitled to request extra <br /> compensation by giving Notice and following the procedures of 1-04.5 NOTICE BY THE <br /> CONTRACTOR and 1-09.11 DISPUTES AND CLAIMS within five (5)calendar days of each <br /> occurrence. The Contractor shall not submit a Contract Claim for possession by the City of <br /> portions of the Work specifically required in the Contract Documents to be placed into use or <br /> operation or both before completion of the entirety of the Work. <br /> 1-08.10(12) Possession of Incomplete Portions of the Project <br /> (******) <br /> Should the Contractor fail to meet any date specified for Substantial Completion or Physical <br /> Completion of Work or any portion of Work requiring early possession and use by the City,the <br /> City may, after a 14 calendar day Notice to the Contractor,take over such portion or any Work <br /> that is behind schedule. In such case, the City's Representative will prepare a list of incomplete <br /> Work taken over by the City. The cost of City's work will be charged to and deducted from <br /> amounts due to the Contractor. The Substantial Completion date of the entire or a portion of the <br /> Project will be established as the date when the City actually begins using the Project or portion <br /> of the Project for its intended purpose. Division of responsibilities between City and Contractor, <br /> HAYES STREET REGULATOR February,2017 <br /> AND CSO CONTROLS (SRO1,SRO2,AND SRO3) <br /> WO No—UP3398-31 SP - 113 <br />