Year io Monitoring of the Smith Island/Union Slough Habitat Restoration Site Everett Public Works <br /> Anticipated Year io Monitoring Task Schedule <br /> 2017 <br /> April Spring water quality monitoring(2 days) <br /> May Installation of hydrologic data loggers;spring water quality monitoring if not conducted in Apri <br /> June Hydrologic data collection <br /> July Purple loosestrife survey;aerial photo(weather and tide dependent);sedimentation survey <br /> August Vegetation monitoring;aerial photo if not done in late July <br /> September Summer water quality monitoring(2 days); Data analysis for report <br /> October Data analysis for report <br /> November Preparation of draft Year io report <br /> December Client review and comment on draft report <br /> 2018 <br /> January Finalization and Delivery of Year io Report to Everett for transmittal to Corps and Ecology <br /> February Project management and coordination—minor efforts <br /> March <br /> April <br /> May <br /> June Project management and client coordination—minor efforts—possible response to Corps or <br /> July Ecology comments on Year io report and close out of performance period;additional services <br /> if/as requested <br /> August <br /> September <br /> October <br /> N.I/ <br /> ICF Page 7 <br />