CITY OF EVERETT SPECIAL PROVISIONS I
<br /> Bid Item 15 - Type 2 Saddle Manhole, 108-inch Diam. I
<br /> Measurement and Payment: Unit Price per Each
<br /> Measurement for furnishing and installing Type 2 Saddle Manhole, 108-inch Diam., will be
<br /> per each, installed in conformance with the Contract Documents.
<br /> Payment for furnishing and installing Type 2 Saddle Manhole, 108-inch Diam., will be made
<br /> at the unit price bid per each, which will be complete compensation for all labor, equipment,
<br /> materials, hauling, locating all existing utilities and potholing in advance for horizontal and
<br /> vertical location, excavation, removal and disposal of waste material, placement and
<br /> compaction of foundation material, the manhole base with required saddle cut-outs and
<br /> stub, manhole barrel, manhole grade rings, manhole rungs or ladder, manhole frame and
<br /> cover, channeling the manhole, installation, final adjustment of structure to grade,
<br /> appurtenances, connections to existing and new pipes, stockpile and placement of
<br /> subsequent backfill (native) materials, compaction, cleaning, temporary pavement patching,
<br /> etc. required to complete the Work in conformance with the Contract Documents. Select
<br /> imported backfill materials are included in other bid items.
<br /> Bid Item 16 - Type 1 Catch Basin
<br /> Measurement and Payment: Unit Price per Each
<br /> Measurement for furnishing and installing Type-1 catch basin will be per each for each
<br /> Type-1 catch basin installed in conformance with the Contract Documents.
<br /> Payment for furnishing and installing Type-1 catch basin will be made at the unit price bid
<br /> per each, which will be complete compensation for all labor, equipment, materials, hauling,
<br /> locating all existing utilities and potholing in advance for horizontal and vertical location,
<br /> excavation, removal and disposal of waste material, furnishing and compaction of
<br /> foundation material, Type-1 catch basin, frame and grate, installation, adjustment of frames
<br /> to grade, appurtenances, connections to new storm sewers, stockpile and placement of
<br /> subsequent backfill (native) materials, compaction, cleaning, temporary pavement patching,
<br /> etc. required to complete the Work in conformance with the Contract Documents. Select
<br /> imported backfill materials are included in other bid items.
<br /> Bid Item 17 - Type 2 Catch Basin with Gas Trap
<br /> Measurement and Payment: Unit Price per Each II
<br /> Measurement for furnishing and installing Type-2 catch basin with gas trap will be per each
<br /> for each Type-2 catch basin with gas trap installed in conformance with the Contract11
<br /> Documents.
<br /> Payment for furnishing and installing Type-2 catch basin with gas trap will be made at the
<br /> unit price bid per each, which will be complete compensation for all labor, equipment, I
<br /> materials, hauling, locating all existing utilities and potholing in advance for horizontal and
<br /> vertical location, excavation, removal and disposal of waste material, foundation material,
<br /> Type-2 catch basin with gas trap, frame and grate, installation, adjustment of frames to
<br /> grade, appurtenances, connections to new storm sewers, stockpile and placement of
<br /> subsequent backfill (native) materials, compaction, cleaning, temporary pavement patching,
<br /> etc. required to complete the Work in conformance with the Contract Documents. Select
<br /> imported backfill materials are included in other bid items.
<br /> Bid Item 18 - R4 Regulator Vault
<br /> Measurement and Payment: Lump Sum I
<br /> Measurement for R4 Regulator Vault Work will be based on the percentage of total Work
<br /> complete at the time of measurement.
<br /> 111
<br /> Sewer Regulators R4 and Division B—BID ITEM DESCRIPTIONS May 2017
<br /> R39 Modifications
<br /> WO No—UP3633 SP-8