Project: WFP Operations Building Seismic Retrofit-Rebid <br /> Change Order No.001 <br /> Change Order Effective Date: 7/10/17 <br /> existence of the roofing was not known until construction had started. The WFP Seismic <br /> Retrofit Rebid plans did not show or call for the roofing to be removed. Removal of the <br /> roofing was necessary for installation of the seismic strengthening above room 216. <br /> Payment is for the removal of the roofing. <br /> Work Change Directive—No. 006—FRP Installation in Control Room: WCD—No. <br /> 006 was agreed to in the lump sum amount of$11,971.00 and 7-Working Days. <br /> Justification: - Contract plans were not explicitly clear as to whether shear <br /> strengthening was required only between the joints of the precast floor panels or was <br /> required over the entire area of the floor panels. The subcontractor performing the work <br /> based their bid on only the joints. Per the Structural Engineer the intent of the design <br /> was for shear strengthening both the joints between the panels and the overall area of <br /> the panels. WCD-006 is an agreement between the City and the Contractor to split the <br /> additional costs to install fiberglass reinforced polymer over the entire area of the <br /> precast floor slabs. <br /> Contract Time: <br /> Twenty, (20) Working Days are being added to the contract by change order#1. <br /> END DOCUMENT 006363 <br /> WFP Operations Building Seismic Retrofit-Rebid July 07,2017 <br /> WO#UP3600 006363 -4 <br />