My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
McClure and Sons Inc. 9/28/2017
>
Contracts
>
Capital Contract
>
McClure and Sons Inc. 9/28/2017
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
9/4/2018 10:09:34 AM
Creation date
9/11/2017 10:12:34 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
McClure and Sons Inc.
Approval Date
9/28/2017
Council Approval Date
8/23/2017
Department
Public Works
Department Project Manager
Richard Hefti
Subject / Project Title
Three Lakes Bypass
Public Works WO Number
UP3611
Tracking Number
0000810
Total Compensation
$1,217,490.34
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
McClure and Sons Inc. 4/28/2018 Change Order 1
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
McClure and Sons Inc. 8/22/2018 Change Order 2
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
505
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
' CITY OF EVERETT PUBLIC WORKS 01 32 16 <br /> SPECIAL PROVISIONS CONSTRUCTION PROGRESS SCHEDULE <br /> SECTION 01 32 16 -CONSTRUCTION PROGRESS SCHEDULE <br /> PART 1 -GENERAL <br /> ' 1.1 SECTION INCLUDES <br /> ' A. Submittals. <br /> B. Format. <br /> C. Review and evaluation. <br /> D. Distribution. <br /> 1.2 SUBMITTALS <br /> 1 A. Within seven days after date established in Notice to Proceed, submit draft of proposed <br /> complete bar chart schedule for review. Include written certification that Subcontractors have <br /> reviewed and accepted proposed schedule. <br /> B. Within seven days after joint review, submit revised Progress Schedule. <br /> ' C. Submit updated schedules with each Application for Payment. <br /> D. Schedule Updates: <br /> 1. Overall percent complete,projected and actual. <br /> 2. Completion progress by listed activity and subactivity, to within five working days prior <br /> to submittal. <br /> ' 3. Changes in Work scope and activities modified since submittal. <br /> 4. Delays in submittals or resubmittals, deliveries, or Work. <br /> 5. Adjusted or modified sequences of Work. <br /> ' 6. Other identifiable changes. <br /> 7. Revised projections of progress and completion. <br /> E. Narrative Progress Report: <br /> 1. Submit with each monthly submission of Progress Schedule. <br /> 2. Summary of Work completed during the past period between reports. <br /> ' 3. Work planned during the next period. <br /> 4. Explanation of differences between summary of Work completed and Work planned in <br /> previously submitted report. <br /> 5. Current and anticipated delaying factors and estimated impact on other activities and <br /> ' completion milestones. <br /> 6. Corrective action taken or proposed. <br /> THREE LAKES VALVE BYPASS July 19, 2017 <br /> WO#UP3611 01 32 16 - 1 <br />