CITY OF EVERETT PUBLIC WORKS 01 32 16 <br /> SPECIAL PROVISIONS CONSTRUCTION PROGRESS SCHEDULE <br /> 1.3 FORMAT <br /> A. Computer-generated bar chart schedule to include at least: I <br /> 1. Identification and listing in chronological order of those activities reasonably required to <br /> complete the Work, including: , <br /> a. Subcontract Work. <br /> b. Major equipment design, fabrication, factory testing, and delivery dates including <br /> required lead times. <br /> c. Move-in and other preliminary activities. <br /> d. Equipment and equipment system test and startup activities. <br /> e. Project closeout and cleanup. <br /> f. Work sequences,constraints, and milestones. <br /> 2. Listings identified by Specification Section number. <br /> 3. Identification of the following: <br /> a. Horizontal time frame by year. month, and week. <br /> b. Duration,early start,and completion for each activity and subactivity. <br /> c. Critical activities and Project float. <br /> d. Subschedules to further define critical portions of Work. <br /> 1.4 REVIEW AND EVALUATION <br /> A. Participate in joint review and evaluation of schedules with Engineer at each submittal. ' <br /> B. Evaluate Project status to determine Work behind schedule and Work ahead of schedule. <br /> C. After review,revise schedules incorporating results of review, and resubmit within three days. <br /> 1.5 DISTRIBUTION ' <br /> A. Following joint review, distribute copies of updated schedules to Contractor's Project site file,to <br /> Subcontractors, suppliers,Engineer,Owner, and other concerned parties. <br /> B. Instruct recipients to promptly report, in writing, problems anticipated by projections shown in <br /> schedules. <br /> 1 <br /> PART 2-PRODUCTS-Not Used <br /> PART 3 -EXECUTION-Not Used <br /> END OF SECTION <br /> 1 <br /> THREE LAKES VALVE BYPASS July 19, 2017 <br /> WO#UP3611 01 32 16-2 <br />