6.3 East Clearwell Roof System Demolition Requirements <br /> See Article 5 of the Contract for specific requirements related to obtaining Demolition Notices to <br /> Proceed. <br /> At the East Clearwell, Design-Builder shall: <br /> 1. Provide a detailed demolition plan for the roof showing methods to be used throughout the <br /> demolition, and specifically addressing measures to protect adjacent and nearby structures and <br /> identification of disposal locations. Demolition plan shall also include a schedule, identify <br /> location(s)for demolition debris disposal, and safety measures to be employed during <br /> demolition. <br /> Test glue-laminated beams (existing roof supports), which may contain wood preservative such <br /> as ACA for hazardous materials. Note that the Fixed Design-Build Price shall include disposal of <br /> beams at an appropriately permitted site based on the assumption that they contain ACA. <br /> Should testing reveal that the beams do not contain hazardous material, City shall issue a <br /> deductive change order in the amount equal to the difference between hazardous material <br /> disposal and non-hazardous demolition debris disposal. <br /> 2. Demolish the existing roof and support structures as needed to allow construction of new roof <br /> system.All components associated with the existing roof system that are not required for the <br /> new roof system shall be demolished, except for support columns, which the City desires to <br /> retain to avoid potential floor damage caused by removal. <br /> 3. Demolish the existing interior washdown system and Hypalon curtain. <br /> 4. Protect the operating West Clearwell vents from dust and other demolition related contaminants. <br /> This may include measures such as temporarily blocking a portion of selected vents or installing <br /> temporary filter material over the vents to prevent contaminants from entering the on-line <br /> clearwell. Submit the proposed plan to the Owner's Representative for approval. <br /> 5. Unless otherwise specified, replace all features impacted by the work with new ones of equal or <br /> greater quality and service life expectations including but not limited to,support brackets, <br /> conduit, piping, and connections. <br /> 6. Transport and dispose of demolition debris, including excess soil, at appropriately permitted <br /> facility(ies). Provide the City with copies of all disposal records. <br /> 6.4 Screen House Bridge Demolition <br /> Design-Builder shall: <br /> 1. Demolish Screen House Bridge in general conformance with conceptual design documents <br /> transmitted with RFP (see Table 2.1). <br /> 2. Provide a plan for demolishing the Screen House Bridge addressing measures to be employed <br /> throughout demolition, including measures for protecting adjacent structures, and above-and <br /> below ground infrastructure, and identification of demolition debris disposal locations. Note that <br /> large diameter pipelines that are critical to WFP operations are directly below the Screen House <br /> Bridge, including above-ground and shallow-buried pipes. <br /> 3. Transport and dispose of Screen House Bridge demolition debris, including excess soil, at <br /> appropriately permitted facility(ies). Provide the City with copies of all disposal records. <br /> 6.5 Disposal of Materials Containing Lead and Hazardous Materials <br /> City of Everett September 13,2017 <br /> Water Filtration Plant Clearwell Roof Replacement DB Project Supplementary Conditions Page 22 <br />