Laserfiche WebLink
Project: Water Filtration Plant Programmed Logic <br /> Controllers Replacement Project <br /> Change Order No. 2 <br /> Change Order Effective Date: September 22nd, <br /> 2017 <br /> CITY <br /> Attest: Approved As to Form: <br /> ,ak A A ° Z2iott <br /> Ma � City Cl k City Attorney /�// <br /> Dat:. 90 1 Date: �-0 Yl / <br /> Recommended By: <br /> Construction Project Engineer (if •Engineering Department Director <br /> Manager(if applicable) Manager(if <br /> applicable) applicable) <br /> Date: Date: Date: Date: <br /> CONTRACTOR <br /> By ,1� Date: 2/�/2.‘'/7 <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> Change Order#2 adds one (1) new item to the Contract as follows: <br /> New item#026—Contractor Compensation for Owner Caused Delay Unrelated to Extra Work. <br /> Extended or Unabsorbed Overhead in the lump sum amount of$99.895.00 <br /> The total increase cost to the contract as a result of adding the above one (1) new item comes to <br /> $99,895.00 <br /> Page 3 of 4 <br />