Project: Water Filtration Plant Programmed Logic <br /> Controllers Replacement Project <br /> Change Order No. 2 <br /> Change Order Effective Date: September 22nd, <br /> 2017 <br /> JUSTIFICATION: <br /> Item#026—Contractor Compensation for Owner Caused Delay Unrelated to Extra Work. Per <br /> section 12.4.3 of the WFP PLC Replacement contract the contractor may request an adjusted of the <br /> contract sum for Extended or Unabsorbed Overhead. The contract sum shall be adjusted using the <br /> Eichleay formula detailed in section 9.5.3. <br /> CONTRACT TIME: <br /> By this Change Order#2 the new agreed date for Completion of the work on the Water Filtration Plant <br /> Programmed Logic Controllers Replacement Project will be October 31St, 2017. <br /> Page 4 of 4 <br />