SHANNON NWIL.SON,INC, <br /> within 24 hours of the survey being taken. Maximum structural displacement criteria of the , <br /> wharf should be determined by MN. Excess displacements may require the contractor to modify <br /> their means and methods of construction. <br /> 7.3 Plans Review and Construction Observation <br /> At the time of this report, Shannon&Wilson, Inc. has been engaged in the review of the design ' <br /> plans and specifications for the work described in this report. We recommend that Shannon& <br /> Wilson, Inc. continue to be retained to review those portions of the plans and specifications that <br /> pertain to the wharf upgrade,to determine if they are consistent with our recommendations. We <br /> recommend that we be retained to observe the geotechnical aspects of construction, including the <br /> pile installation,to provide a geotechnical evaluation of whether the work is accomplished in I <br /> accordance with the plans, specifications and our recommendations and that subsurface <br /> conditions inferred by pile driving logs are representative of the assumed subsurface conditions <br /> in this report. <br /> 8.0 LIMITATIONS <br /> The analyses, conclusions, and recommendations contained in this report are based upon site <br /> conditions as they presently exist, and further assume that the explorations arc representative of <br /> the subsurface conditions within the proposed retrofit area. The primary assumption is that the <br /> subsurface conditions everywhere are not significantly different from those disclosed by the <br /> explorations. Within the limitations of the scope, schedule, and budget,the analyses, , <br /> conclusions, and recommendations presented in this report were prepared in accordance with <br /> generally accepted professional geotechnical engineering principles and practice in this area at <br /> the time this report was prepared. We make no other warranty, either express or implied. Our <br /> conclusions and recommendations were based on our understanding of the project as described <br /> in this report and the site conditions as interpreted from the explorations. I <br /> If, during construction, subsurface conditions different from those encountered in the field <br /> explorations are observed or appear to be present during excavations and pile installation,we i <br /> should be advised at once so that we can review these conditions and reconsider our <br /> recommendations where necessary. If there is substantial lapse of time between the submission <br /> of this report and the start of work at the site, or if conditions have changed due to natural causes <br /> or construction operations at or adjacent to the site,we recommend that we review our report for <br /> the applicability of our recommendations considering the changed conditions and time lapse. I <br /> 21-1-21962-003-R2.docx/wp/cp 21-1-21962-003 <br /> 14 <br />