I <br /> CITY OF EVERETT PUBLIC WORKS 00 72 13 <br /> ISPECIAL PROVISIONS GENERAL CONDITIONS <br /> organized as to facilitate assessment of work and payment of Subcontractors; and be <br /> I balanced. To the greatest extent possible,the breakdown shall use the same tasks or units as <br /> the Contractor's schedule. Contractor shall provide documentation substantiating the cost <br /> allocation if asked by the Owner's Representative. Upon acceptance of the Schedule of <br /> I Values by the Owner's Representative, it shall be used as a basis for all requests for <br /> payment. <br /> B. Progress Payments <br /> 1 1. Payment Request Procedures: <br /> a. By the tenth day of each month, or by schedule mutually agreed upon in writing by the <br /> Contractor and Owner's Representative, the Contractor shall submit to the Owner's <br /> I Representative a partial payment estimate filled out and signed by the Contractor <br /> covering acceptable Work performed during the previous month, or since the last partial <br /> payment estimate was submitted. Contractor's submission of a progress pay estimate <br /> I constitutes a material representation by the Contractor that it performed all of the Work <br /> described in the progress pay estimate during the relevant time period in a workmanlike <br /> manner and that the materials for which payment is requested reasonably conform to <br /> I the Specifications and are either on the job Site or have been installed. If requested by <br /> the Owner's Representative, the Contractor shall provide such additional data as may be <br /> reasonably required to support the payment estimate. Such data may include <br /> I satisfactory evidence of payment for Equipment, materials and labor including <br /> payments to Subcontractors and Suppliers. Certified invoices by the Suppliers shall <br /> accompany a request for payment for delivered Equipment and material. Such <br /> Equipment and material shall be suitably and safely stored at the Site of the.Work. <br /> IPayment requests shall summarize accepted operating and maintenance material with <br /> request for Equipment payment. A progress payment is preliminary only. By making a <br /> progress payment, the Owner does not waive or release its right,nor is it estopped from <br /> I asserting, that previous progress payments were not earned or were in error, whether in <br /> whole or in part. <br /> I 2. Review Procedures: <br /> a. The Owner's Representative will review the estimate and either indicate in writing to <br /> the Owner his or her concurrence with the estimate and his or her recommendation that <br /> payment be made, or indicate in writing to the Contractor his or her reasons for not <br /> I concurring with the estimate. If the Owner's Representative recommends payment and <br /> the Owner concurs, the Owner will pay the Contractor a progress payment on the basis <br /> - of the approved partial payment estimate, less retainage and any amounts the Owner <br /> I may withhold pursuant to Contract or law. The recommendation of the Owner's <br /> Representative is not conclusive, final or binding upon the Owner. <br /> b. In the event the Owner's Representative does not concur with the estimate, the <br /> 1 Contractor may make the changes necessary to obtain the Owner's Representative's <br /> concurrence and resubmit the partial payment estimate, or submit the original progress <br /> payment estimate directly to the Owner, indicating in writing its reasons for refusing to <br /> I make the changes necessary to obtain concurrence. <br /> 3. Retained Percentage <br /> a. As provided in Retainage, the Owner will retain five percent (5%) of all progress <br /> IIpayments. <br /> 4. Withholding <br /> I <br /> Legion Golf Course Stormwater Detention Project November 28, 2017 <br /> IWO#UP3620 00 72 13 -39 <br />