I <br /> CITY OF EVERETT PUBLIC WORKS 00 72 13 <br /> SPECIAL PROVISIONS GENERAL CONDITIONS <br /> 5. The Contractor believes it is required or directed to perform work that is outside the scope of <br /> the Contract Documents; or <br /> 6. An event occurs, or fails to occur, that the Contractor believes, or should reasonably foresee, <br /> may result in a Contract Claim; <br /> B. Timely and adequate Notice is a condition precedent to a Contract Claim. <br /> C. Requests for extensions of Contract Time must be made and will be evaluated in accordance with <br /> 5.2C. Extensions of Contract Time. <br /> D. Irrespective of any request for additional compensation or Contract Time or any Contract Claim <br /> that work is extra and not part of the original scope of Work, the Contractor shall proceed <br /> expeditiously and promptly with the work as the Owner orders. <br /> E. Failing to follow procedures. <br /> II. If the Contractor fails to follow the procedures of this Contract, including failing to give <br /> Notice,the Contractor completely waives such Contract Claim. <br /> 2. In its sole discretion, the Owner may waive strict compliance with procedures, but any such <br /> waiver of one or more items or elements does not waive the necessity for Contractor's strict <br /> compliance with any other item or element, nor shall such waiver be admissible in any legal <br /> proceeding for any reason. <br /> 10.2 Form of Notice <br /> A. The Notice must include the following minimum information: <br /> 1. A complete and accurate description of the event or events giving rise to the Notice, <br /> including dates,times, and locations; <br /> 2. A preliminary list of persons of involved in such event; <br /> 3. A statement whether the Contractor believes the event may result in a Contract Claim for <br /> additional Contract Time or adjustment of the Contract Sum; <br /> 4. A date by which Contractor shall begin providing Supplemental Information as provided in <br /> this section. <br /> 10.3 Supplemental Information <br /> A. Contractor shall supplement the written Notice as soon as possible with a written statement <br /> providing the following: <br /> 1. The date of the event, incident,direction, and other pertinent information; <br /> 2. The nature and circumstances giving rise to the Notice; <br /> 3. The Contract provisions relating to,but not limited to,the event, incident, and direction; <br /> 4. The estimated dollar cost, if any, of the Extra Work, or Delay, or both and how that estimate <br /> was determined; and <br /> 5. An analysis of the schedule showing the schedule change or disruption if the Contractor is <br /> asserting a schedule change or disruption. <br /> B. Contractor Records. <br /> I <br /> Legion Golf Course Stormwater Detention Project November 28, 2017 <br /> WO#UP3620 00 72 13 - 51 <br />