Stormwater Pollution Prevention Plan <br /> The BMP implementation schedule listed below is keyed to proposed phases of the construction <br /> project, and reflects differences in BMP installations and inspections that relate to wet season <br /> construction. The project site is located west of the Cascade Mountain Crest. As such,the dry <br /> season is considered to be from May 1 to September 30 and the wet season is considered to be <br /> from October 1 to April 3. <br /> • Install stabilized construction entrance and access road: TBD <br /> • Begin rough grading: TBD <br /> • Relocate utilities and establish temporary power: TBD <br /> • Begin mass excavation for detention: TBD <br /> • Excavate and install new utilities and services: TBD <br /> • Excavation and site grading ends: TBD <br /> • Begin implementing soil stabilization and sediment control BMPs throughout the site in <br /> preparation for wet season: TBD <br /> • Wet Season starts: 10/01/2016 <br /> • Site inspections and monitoring conducted weekly and for applicable rain events as <br /> detailed in Section 6 of this SWPPP: <br /> • Implement Element#12 BMPs and manage site to minimize soil disturbance during the <br /> wet season: TBD <br /> • Begin asphalt pour: TBD <br /> • Begin building construction: TBD <br /> • Dry Season starts: 05/01/2016 <br /> • Site grading begins: TBD <br /> • Building core/shell construction complete: TBD <br /> • Final landscaping and planting begins: TBD <br /> • Building interior construction complete: TBD <br /> • Project Completion: TBD <br /> 15 <br />