Laserfiche WebLink
I1 F1-08.5.OPT7.FRI.DOCX <br /> 2 (March 13, 1995) <br /> I 3 <br /> 4 This project shall be physically completed within *** fifty-four (54) *** working days. <br /> 5 <br /> I 6 1-08.9.RTF <br /> 7 1-08.9 Liquidated Damages <br /> 8 (August 14, 2013 APWA GSP) <br /> 19 <br /> 10 Revise the fourth paragraph to read: <br /> 11 <br /> I12 <br /> 13 When the Contract Work has progressed to Substantial Completion as defined in the <br /> Contract, the Engineer may determine that the work is Substantially Complete. The <br /> 14 Engineer will notify the Contractor in writing of the Substantial Completion Date. For <br /> 15 overruns in Contract time occurring after the date so established, the formula for <br /> I <br /> 16 liquidated damages shown above will not apply. For overruns in Contract time occurring <br /> 17 after the Substantial Completion Date, liquidated damages shall be assessed on the <br /> 18 basis of direct engineering and related costs assignable to the project until the actual <br /> 1 19 Physical Completion Date of all the Contract Work. The Contractor shall complete the <br /> 20 remaining Work as promptly as possible. Upon request by the Project Engineer, the <br /> 21 Contractor shall furnish a written schedule for completing the physical Work on the <br /> I 22 Contract. <br /> 23 <br /> 24 1-09.GR1 <br /> I 25 Measurement and Payment <br /> 26 <br /> 27 1-09.6.RTF <br /> I 28 1-09.6 Force Account <br /> 29 (October 10, 2008 APWA GSP) <br /> 30 <br /> I 31 Supplement this section with the following: <br /> 32 <br /> 33 The Contracting Agency has estimated and included in the Proposal, dollar amounts for <br /> 34 all items to be paid per force account, only to provide a common proposal for Bidders. <br /> I <br /> 35 All such dollar amounts are to become a part of Contractor's total bid. However, the <br /> 36 Contracting Agency does not warrant expressly or by implication, that the actual amount <br /> 37 of work will correspond with those estimates. Payment will be made on the basis of the <br /> I <br /> 38 amount of work actually authorized by Engineer. <br /> 39 <br /> 40 1-09.8.GR1 <br /> I 41 Payment For Material On Hand <br /> 42 <br /> 43 1-09.8.INSTI.GR1 <br /> I 44 The last paragraph of Section 1-09.8 is revised to read: <br /> 45 <br /> 46 1-09.8.OPT1.GR1 <br /> I 47 (August 3, 2009) <br /> 48 The Contracting Agency will not pay for material on hand when the invoice cost is less <br /> 49 than $2,000. As materials are used in the work, credits equaling the partial payments <br /> 50 for them will be taken on future estimates. Each month, no later than the estimate due <br /> I <br /> 51 date, the Contractor shall submit a letter to the Engineer that clearly states: 1) the <br /> 52 amount originally paid on the invoice (or other record of production cost) for the items <br /> 53 on hand, 2) the dollar amount of the material incorporated into each of the various work <br /> 1 54 items for the month, and 3) the amount that should be retained in material on hand <br /> HOT MIX ASPHALT OVERLAY-2018 PAGE 31 OF 57 March 6,2018 <br /> I WORK ORDER#3667 <br /> SPECIAL PROVISIONS <br />