Project: Portal 1 Replacement <br /> Change Order No.01 <br /> Change Order Effective Date: 6/21/18 <br /> the end prepared for welding of the new adapter pipe. The adapter pipe was then <br /> welded to the pipe spool in the wall of the new portal and to the 90" end of the <br /> reducer pipe. Two days are being added to cover the additional time to remove <br /> the mortar, cut and prepare the existing pipe and the additional welding. <br /> END DOCUMENT 006363 <br /> Portal 1 Replacement June 21,2018 <br /> WO#UP3602 006363 -4 <br />