2. Failure to comply strictly and timely shall be deemed a waiver of the Contract Claim. <br /> B. Extra Work <br /> 1. Adjustment of Contract Sum <br /> a. If the Contractor is entitled to an adjustment of Contract Sum because of Extra Work, <br /> the adjustment shall be calculated and paid as provided in 9.5. Adjustment Of <br /> Contract Sum. <br /> ' 1) This amount includes jobsite and home office Overheads for such Work, <br /> including any schedule delays relating to such Work. <br /> 2) No compensation in addition to that provided in 9.7. Force Account shall be <br /> paid for such thing as extended Overhead or other costs or damages. <br /> b. Extension of Contract Time <br /> 1) Extensions of Contract Time caused by Extra Work shall be determined as <br /> provided in 5.2.C. Extensions of Contract Time. <br /> C. Delays <br /> 1. Owner Caused Delay Unrelated to Extra Work <br /> ' a. Adjustment of Contract Sum <br /> 1) If the Contractor is entitled to an adjustment of Contract Sum because of a Delay <br /> solely caused by the Owner that does not relate to Extra Work, Contractor shall <br /> ' only be compensated for the items below, less all funds paid pursuant to any <br /> change in the Contract Sum that contributed to the Delay: <br /> a) Documented, incurred cost of nonproductive field supervision or labor <br /> extended because of the Delay; <br /> ' b) Documented, incurred cost of home office supervision to attend jobsite <br /> meetings; <br /> c) Documented, incurred cost of temporary facilities or equipment rental <br /> ' extended because of the Delay; <br /> d) Documented, incurred cost of insurance extended because of the Delay; <br /> e) General and administrative Overhead in an amount to be agreed upon, but <br /> ' not to exceed three percent of original Contract Sum divided by the Contract <br /> Time for each day of the Delay. <br /> 2) Owner shall not owe Contractor compensation for extended Overhead or other <br /> delay costs where Contractor contributed to or is concurrently responsible for the <br /> ' Delay. <br /> b. Adjustment of Contract Time <br /> 1) If the Contractor is entitled to an adjustment of Contract Time because of a Delay <br /> ' solely caused by the Owner that does not relate to Extra Work, Contractor shall <br /> be entitled to an adjustment of Contract Time to the extent the Delay increases <br /> the duration of the Project, as measured by the critical path and as demonstrated <br /> pursuant to the requirements of 5.2.C. Extensions of Contract Time. <br /> 2. Contractor Caused Delay <br /> a. If the Contractor is solely responsible for any Delay to any interim milestone, <br /> Substantial Completion, Physical Completion or the Completion Date, the Owner shall <br /> ' be entitled to liquidated or other damages as provided elsewhere in the Contract <br /> Documents. <br /> b. The Contractor accepts the risk of any Delays caused by strikes, work slowdowns,job <br /> actions and labor unrest of any kind. <br /> c. Contractor shall not be entitled to any increase in Contract Sum or Contract Time due <br /> to a Delay it caused. <br /> ' PROCESS WATER PUMP STATION 06/13/2017 <br /> WO-3647 00 72 13 - 55 <br />