Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> 4. Show Submittal preparation, submission, review, and breakdown at a <br /> minimum. Show individual parts of major Submittals. <br /> Contractor shall identify any and all Work furnished by City and installed by City on <br /> the construction schedule. <br /> 1-08.3(4) Measurement <br /> Delete 1-08.3(4). <br /> 1-08.3(5) Payment <br /> Delete 1-08.3(5) and substitute the following: <br /> Costs incurred in performance of this Work shall be included in the contract bid <br /> items and no direct compensation shall be paid. <br /> 1-08.4 Prosecution of Work <br /> Delete 1-08.4 and substitute the following: <br /> 1-08.4 Notice to Proceed and Prosecution of Work <br /> (******) <br /> The City will issue a Notice to Proceed after the Contract has been executed and the Contract <br /> Bond and evidence of insurance have been approved and filed by the City. The Contractor <br /> shall not commence with the Work until the Notice to Proceed has been given by the City. <br /> The Contractor shall commence construction activities on the Project site within 14 calendar <br /> days of the Notice to Proceed Date, unless otherwise approved in writing. The Contractor <br /> shall diligently pursue the Work to the Physical Completion Date within the time specified in <br /> the Contract. Voluntary shutdown or slowing of operations by the Contractor shall not relieve <br /> the Contractor of the responsibility to complete the Work within the time(s) specified in the <br /> Contract. <br /> The City is not obligated to accept or pay for Work performed by the Contractor or be liable <br /> for any Delays, prior to delivery of the Notice to Proceed. The City's knowledge of Work <br /> being performed prior to delivery of the Notice to Proceed will not obligate the City to accept <br /> or pay for such Work. Contractor waives any and all Contract Claims for an adjustment of <br /> Contract Sum or Contract Time arising out of, or related to, Work it performs prior to receipt <br /> of the Notice to Proceed. <br /> The City may issue partial Notices to Proceed. Contractor may seek permission in writing to <br /> perform some Work prior to issuance to the Notice to Proceed, such as shop drawings, <br /> equipment and material Submittals, or surveying and the City or City's Representative may, <br /> in its sole discretion, approve in writing such Work prior to the issuance of the Notice to <br /> Proceed. <br /> Supplement 1-08.4 by adding the following: <br /> 1-08.4(1) Construction Progress <br /> The Contractor shall furnish all labor, materials, facilities and Equipment necessary to <br /> ensure the prosecution and completion of the Project within the interim milestones, <br /> Substantial Completion, Physical Completion and Completion Dates of the Contract. If <br /> Work falls seven calendar days or more behind the reviewed Preliminary Schedule, the <br /> Contractor agrees that, at its sole cost and expense, it will take all actions necessary to <br /> return the Project to the accepted schedule. These actions may include the following: <br /> a. Increase labor in quantities and crafts. <br /> b. Increase the number of working hours per shift, shifts per working day, <br /> working days per week, or the amount of Equipment, or any combination of <br /> the foregoing. <br /> Wetmore Ave Stormwater Bypass Division 1 —GENERAL REQUIREMENTS August, 2018 <br /> WO No—UP3704 SP—1-94 <br />