1 <br /> F. POSSESSION OF INCOMPLETE PORTIONS OF THE PROJECT <br /> A. Should the Contractor fail to meet any date specified for Substantial Completion of Work or any portion of <br /> work requiring early possession and use by the Owner, the Owner may, after a ten-day notice to the <br /> Contractor, take over such portion or any Work that is behind schedule. In such case, the Owner's <br /> Representative will prepare a list of incomplete Work taken over by the Owner. The cost of Owner's work <br /> will be charged to and deducted from amounts due to the Contractor. The Substantial Completion date of <br /> the entire or a portion of the Project will be established as the date when the Owner actually begins using <br /> the Project or portion of the Project for its intended purpose. Division of responsibilities between Owner <br /> and Contractor,beginning of warranties, and any other issues relating to Substantial Completion shall be as <br /> specified in 5.7. Substantial Completion. <br /> G. SUBSTANTIAL COMPLETION <br /> A. When the Contractor considers the Work to be Substantially Complete and ready for its intended use, it <br /> shall give Notice to the Owner's Representative. The Notice shall include an itemized list of remaining <br /> incomplete Work. If the Owner's Representative determine the Work is not substantially complete, the <br /> Contractor will be notified in writing, identifying the reasons for such a determination. <br /> 1. If the Owner's Representatives find the Work substantially complete, he or she will meet with the <br /> Contractor to: <br /> a. Prepare a Punch List of incomplete items of Work. <br /> b. Define the division of responsibility between Owner and Contractor with respect to security, <br /> operation,maintenance,heat, utilities,insurance, and warranties. <br /> c. Describe any other issues related to acceptance of the substantially completed Work. I <br /> B. If the Owner's Representative is not an employee of the Owner, the Owner's Representative will write to <br /> the Owner upon reaching agreement with the Contractor,certifying that the Work is substantially complete, <br /> listing the items of incomplete Work, stating the date for completion of incomplete Work, defining the <br /> division of responsibilities, and setting forth any other terms related to acceptance. In such event, the <br /> Owner will review the Owner's Representative's certification that the Work is substantially complete. If <br /> the Owner concurs, the Owner will notify the Contractor in writing that the Work is accepted as <br /> substantially complete. Except for any portion(s)of Workspecified for early completion or required by the <br /> Owner for early possession, Substantial Completion will not occur for any Work until the entire Project is <br /> ready for possession and use. The acceptance notice will include a Punch List of incomplete Work items <br /> and corrective Work, set the date for their completion and repair, describe the division of responsibility <br /> between the Owner and Contractor, and describe any other terms of acceptance. The Contractor will <br /> acknowledge receipt of the acceptance notice in writing, indicating acceptance of all of its terms and <br /> provisions. ' <br /> C. Subsequent to the Substantial Completion date, the Owner may exclude the Contractor from the Work <br /> during such periods when construction activities might interfere with the intended operation of the Project. <br /> The Owner, however, shall allow the Contractor reasonable access for completion or correction of <br /> incomplete Punch List items. <br /> I <br /> 10023829 City of Everett Public Works July 2018 <br /> WPCF FEN Chlorination Building Upgrade Work Order 3614 <br /> GENERAL CONDITIONS <br /> 00 72 13-26 Issue for Bid I <br />