Project: Grand Avenue Park Bridge <br /> Change Order No.: 6 <br /> Change Order Effective Date: 10-17-2018 <br /> CONTRACTOR <br /> OCT2 2 2018 <br /> By Date: <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> Extension of Time due to Operatinff Enffineers Local 302 Strike—Per Standard Specification 1-08.8, <br /> Extensions of Time, may be granted for Strikes. Interwest provided appropriate Notice in SL-028 on <br /> 8/21/18 and the request for extension in SL-031, dated 9/7/18. <br /> Exhibit B—Additional Contract Time: <br /> This change order adds 9 (nine)working days to the contract. <br /> Exhibit C—Existingand New Bid Item(s) <br /> � ) <br /> No New Bid Items. <br /> Measurement and Payment <br /> N/A <br /> ATTACHMENT ONE FOLLOWS(Additional Page) <br /> • Interwest Construction Serial Letter 028, dated 8/21/18 <br /> • Interwest Construction Serial Letter 031, dated 9/7/18 <br /> Page 3 of 3 <br />