GE 0 DES1GNP FIELD REPORT <br /> Project Name: Everett River Front-Simpson Report: 068 <br /> GeoDesign#: Polygon-127-03 Date: 08/03/2017 <br /> Reports with Unresolved Nonconformance Issues: Permit: <br /> PW 1505-005 <br /> Nick Abdelnour(Polygon) Randy Allen(City of Everett) Weather.Clear,60-80's <br /> Ron Bowen(Polygon) Eddy Stevens(Polygon) Arrival/Departure: 1015/1415 <br /> Distribution: <br /> Doug Ross(Polygon) Kirk Keck(City of Everett) <br /> Paul McKee(City of Everett) 1 Dave Foster(City of Everett) Prepared By: Ben Weinberg, EIT <br /> m Site Plan(s) 0 Density Test Summary Signature: 7,4-- <br /> Attachments: 0 Installation Records m Other Reviewed By: RL <br /> PURPOSE of VISIT:GeoDesign representative, Ben Weinberg,was on-site part time at the request of Leroy with BDZ to <br /> observe foundation subgrade for Lots 246 and 247. <br /> SUMMARY of OBSERVATIONS: <br /> LOT 246: <br /> Previously GeoDesign noted that BDZ had over-excavated the east 2/3 of the Lot 246 area approximately 4 to 5 feet down <br /> to firm and unyielding material and partially backfilled the area with a cement-treated material.Today, GeoDesign noted that <br /> the contractor completed over-excavation and backfilling the over-excavated areas to near plan bottom of footing. <br /> GeoDesign noted that the cement dust was added to stockpiles of material outside the foundation area and thoroughly <br /> mixed using the bucket of an excavator. GeoDesign noted that the material was mixed, placed,and spread in <br /> approximately 18 inch loose lifts using a Komatsu PC300 excavator and compacted into a firm and unyielding mass using <br /> an excavator-mounted hoepack(AM)and a smooth-drum vibratory roller(PM). Penetration depths encountered for the <br /> material placed could generally be probed 2-4 inches shortly after compaction;the top 1.5 feet of material for the west 1/3 of <br /> the lot area could be probed 1.5 feet shortly after compaction,which appeared to be associated with its higher moisture <br /> content. GeoDesign will verify that the cement treated material cures into a firm and unyielding mass at a later date. <br /> LOT 247: <br /> Today, GeoDesign noted that BDZ completed excavation of the east 1/3 of the Lot 247 area down to firm and unyielding <br /> material,which required 4-5 feet of over-excavation, using a Komatsu PC300 excavator. GeoDesign noted that the <br /> exposed base of the over-excavated area generally consisted of a gray-brown silty SAND with gravel which could be <br /> probed less than 2 inches using a 1/2 inch diameter soil probe. After observing the base of the over-excavated area, <br /> GeoDesign notified Leroy with BDZ that the over-excavated lot area was currently suitable for placement of backfill material. <br /> No backfill material was placed for the over-excavated area for Lot 247 today. <br /> This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering or environmental services.We rely on the contractor to comply with the plans and <br /> spedfications throughout the duration of the project irrespective of the presence of our representative.Our work does not indude supervision or direction of the contractor,the contractor's employees <br /> or agents.Our firm is not responsible for site safety.This field report is a DRAFT representation of our field observations,testing,and preliminary recommendations.The report can only be considered <br /> final upon review of the GeoDesign project manager,as indicated by initials in the"Reviewed By"section. <br /> 10700 Meridian Avenue North,Suite 402 I Seattle,WA 98133 I 206.838.9900 <br /> 2502 Jefferson Avenue I Tacoma,WA 98402 I 253.203.0095 <br /> 7. <br />