My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Interwest Construction Inc 12/27/2018
>
Contracts
>
Capital Contract
>
Interwest Construction Inc 12/27/2018
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
7/17/2019 10:32:06 AM
Creation date
1/15/2019 9:47:50 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Interwest Construction Inc
Approval Date
12/27/2018
Council Approval Date
12/5/2018
Department
Public Works
Department Project Manager
Richard Hefti
Subject / Project Title
Watermain Replacement T
Public Works WO Number
UP3684
Tracking Number
0001600
Total Compensation
$2,106,730.68
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
Interwest Construction Inc. 3/6/2019 Change Order 1
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
Interwest Construction Inc. 5/23/2019 Change Order 2
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
INTERWEST CONSTRUCTION INC. 6/19/2019 Change Order 3
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
319
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
CITY OF EVERETT SPECIAL PROVISIONS <br /> than the benefit of the Project. Contractor shall use its best efforts in good faith to 111 <br /> minimize dependencies, minimize the number of critical paths, and schedule the <br /> Project to be complete as expeditiously as reasonably possible. <br /> Contractor shall submit with each application for payment or progress pay estimate an <br /> updated progress schedule, but no less often than monthly. If requested by the City's <br /> Representative or the City, Contractor shall prepare and submit updated progress <br /> schedules from time to time that may be more frequent than monthly. <br /> The Contractor hereby expressly agrees and acknowledges that any failure by <br /> Contractor to provide accurate, complete, current and updated schedules at least <br /> monthly constitutes a waiver of any and all claims or requests for adjustment of <br /> Contract Sum or Time that arise out of, result from, or are caused by, any Delay on the <br /> Project or scheduling of the Work. Timely submission of updated schedules at least <br /> monthly is a condition precedent to any later or subsequent Contract Claim or request <br /> for an adjustment of either Contract Sum or Time related to or arising out of time, an <br /> alleged Delay, or the schedule or sequence of Work. Similarly, the parties agree the <br /> City may withhold progress pay estimates if updated schedules are not timely <br /> submitted monthly. These remedies are cumulative and not exclusive of other remedy. <br /> The City's use of one or more of these remedies does not constitute an election or <br /> prevent the City from pursuing other remedies for this or other defaults. <br /> No later than the pre-construction conference, Contractor shall submit a preliminary <br /> schedule ("Preliminary Schedule") for the entire Work to City's Representative and <br /> City. Contractor shall prepare such schedule in consultation with its Subcontractors. <br /> 1-08.3(2) Project Schedule Types <br /> Delete 1-08.3(2), including its subsections, and substitute the following: <br /> 1-08.3(2) Project Schedule Requirements For Contracts Exceeding $500,000 <br /> (******) <br /> 1-08.3(2)A Scheduler <br /> Contractor represents and warrants that it employs, or will engage prior to <br /> preparation of the Preliminary Schedule, a qualified scheduler. A "qualified <br /> scheduler" is a person who has at least five years of full time, construction project <br /> scheduling experience, who is familiar, competent and professional in creating, <br /> maintaining and updating time scaled and resource loaded critical path schedules. <br /> Contractor shall submit to the City the name. address, and qualifications of the <br /> qualified scheduler to the City for approval no later than the pre-construction <br /> conference. <br /> 1-08.3(2)B Baseline Schedule <br /> The progress schedule submitted to the City's Representative and City after their <br /> review of the Preliminary Schedule shall be the Baseline Schedule. The Baseline <br /> Schedule shall be the baseline schedule against which all future schedules are <br /> compared and updated, and job progress is measured. The Baseline Schedule <br /> shall not be reset or changed without the written agreement of City's <br /> Representative and City. <br /> 1-08.3(2)C Updates <br /> Contractor shall submit with each application for payment or progress pay <br /> estimate an updated progress schedule, but no less often than monthly. If <br /> requested by City's Representative or the City. Contractor shall prepare and <br /> submit updated progress schedules from time to time, which may be more <br /> frequent than monthly. i <br /> Watermain Replacement"T" Division 1 —GENERAL REQUIREMENTS October 10, 2018 <br /> WO No—UP3684 SP—98 ' <br />
The URL can be used to link to this page
Your browser does not support the video tag.