1• <br /> for the Contractor to all employees). Mobilization also includes the costs incurred during <br /> demobilization applies to both force account and other contract work. The Contracting Agency <br /> will pay for mobilization for off-site preparatory work for force account items provided that notice <br /> has been provided sufficiently in advance to allow the Engineer to witness the activity, if desired. <br /> Any costs experienced during mobilization activities for labor, equipment, materials or services <br /> shall be listed in that section of the force account summary and paid accordingly. <br /> 9.6.6 For Contractor Markup on Subcontractor's Work. <br /> When work is performed on a force account basis by one or more approved subcontractors, by <br /> lower-tier subcontractors or suppliers, or through invoice by firm(s)acting in the manner of a <br /> subcontractor, the Contractor will be allowed an additional markup, from the table below, applied <br /> to the costs computed for work done by each subcontractor through Sections 1, 2, 3, and 4, to <br /> compensate for all administrative costs, including project overhead, general company overhead, <br /> profit, bonding, insurance, Business&Occupation tax, and any other costs incurred. <br /> A firm may be considered to be acting as a subcontractor when the Engineer observes <br /> one or more of the following characteristics: ' <br /> a. The person in charge of the firm's activities takes an active role in managing the <br /> overall project, including extensive coordination, interpretation of plans, interaction <br /> with the Contracting Agency or management of a complex and interrelated operation. <br /> b. Rented equipment is provided fueled, operated and maintained by the firm. <br /> Operators of rented equipment are supervised directly by the firm's representative. <br /> There is a little interaction between the Contractor and the employees of the firm. <br /> c. The firm appears to be holding the risk of performance and quality of the work. <br /> d. The firm appears to be responsible for liability arising from the work Markups on <br /> Work Preformed by Subcontractor(s); <br /> On amounts paid for work performed <br /> by each Subcontractor on each <br /> force account and calculated Up to $25,0000 12% <br /> through Sections 1-4 <br /> On amounts greater than $25,000 up to$100,000 10% , <br /> On amounts greater than $100,000 7% <br /> The amounts and markup rates shall be calculated separately for each subcontractor on <br /> each force account items established. <br /> The payments provided above shall be full payment for all work done on a force account basis. The 1 <br /> calculated payment shall cover all expenses of every nature, kind and description, including those listed <br /> above and any others incurred on the work being paid through force account. Nothing in this provision <br /> shall preclude the Contractor from seeking an extension of time or time-related damages to unchanged <br /> 111 <br /> work arising as a result of force account work. The amount and costs of any work to be paid by force <br /> account shall be computed by the Engineer and the result shall be final as provided in Section 1-05.1. <br /> An item that has been bid at a unit price or lump sum in the Proposal will not be paid as force account <br /> unless a change as defined in Section 1-04.4 has occurred and the provisions require a payment <br /> adjustment. Items which are included in the Proposal as Force Account or which are added by change <br /> order as Force Account may, by agreement of the parties at any time, be converted to agreed unit prices <br /> or lump sums applicable to the remaining work. <br /> EVERETT RIVERFRONT SURCHARGE GENERAL CONDITIONS <br /> PHASE 3 <br /> 00710-38 <br />