9.1.2. Progress Payments , <br /> 9.1.2.1 Payment Request Procedures: <br /> By the tenth day of each month, or by schedule mutually agreed upon in writing by the Contractor and ' <br /> Owner's Representative, the Contractor shall submit to the Owner's Representative a partial payment <br /> estimate filled out and signed by the Contractor covering acceptable work performed during the previous <br /> month, or since the last partial payment estimate was submitted. Contractor's submission of a progress <br /> pay estimate constitutes a material representation by the Contractor that it performed all of the work <br /> described in the progress pay estimate during the relevant time period in a workmanlike manner and that <br /> the materials for which payment is requested reasonably conform to the specifications and are either on <br /> the job site or have been installed. If requested by the Owner's Representative, the Contractor shall <br /> provide such additional data as may be reasonably required to support the payment estimate. Such data <br /> may include satisfactory evidence of payment for Equipment, materials and labor including payments to <br /> subcontractors and suppliers. Certified invoices by the suppliers shall accompany a request for payment <br /> for delivered Equipment and material. Such Equipment and material shall be suitably and safely stored at <br /> the site of the work. Payment requests shall summarize accepted operating and maintenance material <br /> with request for Equipment payment. A progress payment is preliminary only. By making a progress <br /> payment, the Owner does not waive or release its right, nor is it estopped from asserting, that previous <br /> progress payments were not earned or were in error, whether in whole or in part. <br /> 9.1.2.2 Review Procedures: <br /> The Owner's Representative will review the estimate and either indicate in writing to the Owner his or her <br /> concurrence with the estimate and his or her recommendation that payment be made, or indicate in <br /> writing to the Contractor his or her reasons for not concurring with the estimate. If the Owner's <br /> Representative recommends payment and the Owner concurs, the Owner will pay the Contractor a <br /> progress payment on the basis of the approved partial payment estimate, less retainage and any <br /> amounts the Owner may withhold pursuant to Contract or law. The recommendation of the Owner's <br /> Representative is not conclusive, final or binding upon the Owner. <br /> In the event the Owner's Representative does not concur with the estimate, the Contractor may make the <br /> changes necessary to obtain the Owner's Representative's concurrence and resubmit the partial payment <br /> estimate, or submit the original progress payment estimate directly to the Owner, indicating in writing its <br /> reasons for refusing to make the changes necessary to obtain concurrence. I <br /> 9.1.2.3 Retained Percentage <br /> As provided in section 9.7. Retainage the Owner will retain five percent (5%) of all progress payments. <br /> 9.1.2.4 Withholding <br /> The Owner's Representative may refuse to recommend the whole or any part of any payment if in the <br /> Owner's Representative's opinion it would be incorrect to make such recommendation to the Owner. The <br /> Owner's Representative may also refuse to recommend any such payment, or because of subsequently <br /> discovered evidence or the result of tests, may nullify any such payment previously recommended to <br /> such extent as may be necessary in the Owner's Representative's opinion to protect the Owner from loss <br /> as a result of: I <br /> 1. Defective or damaged work. <br /> 2. A deductive Change Order. <br /> 3. Persistent failure of the Contractor to perform the work in accordance with the Contract <br /> Documents, including failure to maintain the progress of the work in accordance with the <br /> construction schedule. Persistent failure to maintain the progress of the work shall mean <br /> that for a period of two consecutive months following a written Notice from the Owner's <br /> Representative or Owner, the Contractor fails to correct a behind-schedule condition at a <br /> rate that would reasonably indicate that he or she will finish the Project on schedule. <br /> 4. Disregard of authority of the Owner or Owner's Representative or the laws of any public , <br /> body having jurisdiction. <br /> EVERETT RIVERFRONT SURCHARGE GENERAL CONDITIONS I <br /> PHASE 3 <br /> 00710-30 <br />