Bid Item B-31 — BIORETENTION FILTRATION STRUCTURE, 4-FT. X 4-FT (FILTERRA)
<br /> Specification Section 7-06
<br /> Measurement and Payment: Unit Price per Each
<br /> The unit price per each bio-retention structure shall be full compensation for all labor, material, ,
<br /> tools and equipment necessary to satisfactorily complete the work as defined in the Standard
<br /> Specifications, plans and details, these special provisions, and manufactures recommendations
<br /> for the locations where indicated on the plans. ,
<br /> The unit price of per each structure shall also include, but not be limited to, all costs for
<br /> excavation, removing and disposing of existing pipe and/or existing manholes, if necessary,
<br /> hauling and disposing of surplus or unsuitable material, dewatering, furnishing and installing
<br /> treatment medium and all necessary and required appurtenances, placing and compacting
<br /> backfill, furnishing, placing, and compacting foundation material as required, connect to storm
<br /> water pipe system, cleaning installed structure, construction of concrete flume, adjusting access
<br /> covers to final grade, and replacing, protecting and maintaining utilities.
<br /> Bid Item B-32— MODULAR WETLAND SYSTEM, 4-FT. X 8-FT.
<br /> Bid Item B-33 — MODULAR WETLAND SYSTEM, 6-FT. X 8-FT,
<br /> Bid Item B-34— MODULAR WETLAND SYSTEM, 8-FT. X 8-FT.
<br /> Bid Item B-35— MODULAR WETLAND SYSTEM, 8-FT. X 20-FT.
<br /> Specification Section 7-06 ,
<br /> Measurement and Payment: Unit Price per Each
<br /> The unit price per each Modular Wetland System shall be full compensation for all labor, ,
<br /> material, tools and equipment necessary to satisfactorily complete the work as defined in the
<br /> Standard Specifications, plans and details, these special provisions, and manufactures
<br /> recommendations for the locations where indicated on the plans. '
<br /> The unit price of per each structure shall also include, but not be limited to, ail costs for
<br /> excavation, removing and disposing of existing pipe and/or existing manholes. if necessary,
<br /> hauling and disposing of surplus or unsuitable material, dewatering, furnishing and installing
<br /> treatment medium and all necessary and required appurtenances, placing and compacting
<br /> backfill, furnishing, placing, and compacting foundation material as required, connect to storm
<br /> water pipe system, cleaning installed structure, construction of concrete flume, adjusting access
<br /> covers to final grade, and replacing, protecting and maintaining utilities.
<br /> Bid Item B-36 — STORMFILTER SYSTEM (INCLUDES FILTERS)
<br /> Specification Section 7-06
<br /> Measurement and Payment: Unit Price per Each
<br /> The unit price per each for StormFilter System shall be full compensation for all labor, material,
<br /> tools and equipment necessary to satisfactorily complete the work as defined in the Standard
<br /> Specifications, Standard Plans, these specifications and as shown on the Plans.
<br /> Cleveland Avenue Division B—BID ITEM DESCRIPTIONS November 2018
<br /> Sewer System Replacement and
<br /> Storm Water Separation
<br /> WO No. UP3398 SP-42 '