Laserfiche WebLink
Geotechnical Engineering Evaluation NGA File No. 1008917 <br /> Cooley Smiles Commercial Development October 3,2017 <br /> Everett,Washington Page 10 <br /> Structural Fill <br /> General: Fill placed beneath foundations, pavement, or other settlement-sensitive structures should be <br /> placed as structural fill. Structural fill,by definition, is placed in accordance with prescribed methods and <br /> standards, and is monitored by an experienced geotechnical professional or soils technician. Field <br /> monitoring procedures would include the performance of a representative number of in-place density tests <br /> to document the attainment of the desired degree of relative compaction. The area to receive the fill <br /> should be suitably prepared as described in the Site Preparation and Grading subsection of this report <br /> prior to beginning fill placement. Sloping areas to receive structural fill should be benched prior to fill <br /> placement to key the fill into the slope. The benches should be level and have a minimum width of six to <br /> eight feet. The benches should be constructed by cutting into the native sloping ground, then fill can be <br /> placed on the level benches. <br /> Materials: Structural fill should consist of a good quality, granular soil, free of organics and other <br /> deleterious material, and be well graded to a maximum size of about three inches. All-weather structural <br /> fill should contain no more than five-percent fines (soil finer than U.S. No. 200 sieve, based on that <br /> fraction passing the U.S. 3/4-inch sieve). The use of some of the on-site soils as structural fill may be <br /> feasible, but this will be highly dependent on moisture and organic contents of the material at the time <br /> construction takes place. The use of the on-site soils as structural fill during wet weather will be <br /> extremely difficult, if not impossible. We should be retained to evaluate proposed structural fill material <br /> prior to placement. <br /> Fill Placement: Following subgrade preparation, placement of structural fill may proceed. All fill <br /> placements should be accomplished in uniform lifts up to eight inches thick. Each lift should be spread <br /> evenly and be thoroughly compacted prior to placement of subsequent lifts. <br /> All structural fill underlying building areas and pavement subgrade should be compacted to a minimum of <br /> 95 percent of its maximum dry density. Maximum dry density, in this report, refers to that density as <br /> determined by the ASTM D-1557 Compaction Test procedure. The moisture content of the soils to be <br /> compacted should be within about two percent of optimum so that a readily compactable condition exists. <br /> It may be necessary to over-excavate and remove wet soils in cases where drying to a compactable <br /> condition is not feasible. All compaction should be accomplished by equipment of a type and size <br /> sufficient to attain the desired degree of compaction. <br /> NELSON GEOTECHNICAL ASSOCIATES, INC. <br />