Laserfiche WebLink
1 <br /> I. Any requests for extensions in Contract Time, whether resulting from Extra Work directed by the <br /> Owner or not, shall be accompanied by an analysis of schedules using the critical path method. This <br /> analysis shall include an updated schedule, an as-planned schedule, an as-built schedule, a but-for <br /> schedule, and narrative explaining the alleged causes, schedule impacts and all costs related to or <br /> arising out of the proposed extension.Any requests for extensions of Contract Time by the Contractor <br /> shall be submitted in accordance with these General Conditions. Extensions of Contract Time will be <br /> granted only as provided in the General Conditions and to the extent that affected critical activities <br /> exceed the Total Float time along the affected paths of the reviewed Preliminary Schedule at the time <br /> the change was authorized in writing by the Owner. Contractor has the burden of clearly and <br /> convincingly demonstrating entitlement to any adjustment of Contract Time. <br /> 2. If the Owner is solely responsible for any Delay to Substantial Completion, Physical Completion, <br /> Completion Date, or Final Acceptance, the Contractor shall only be entitled to compensation or other <br /> damages as described in 12.4 Remedies, provided that Contractor timely gave Notice pursuant to <br /> ARTICLE 10. NOTICE TO OWNER, timely submitted a Contract Claim pursuant to ARTICLE <br /> 12. CONTRACT CLAIMS and fulfilled the requirements of 5.B. Construction Schedule. <br /> D. Construction Progress <br /> 1. The Contractor shall furnish all labor, materials, facilities and Equipment necessary to insure the <br /> prosecution and completion of the Project within the interim milestones, Substantial Completion, <br /> Physical Completion and Completion Dates of the Contract. If Work falls seven days or more behind <br /> the reviewed Preliminary Schedule,the Contractor agrees that, at its sole cost and expense, it will take <br /> all actions necessary to return the Project to the accepted schedule. These actions may include the <br /> following: <br /> a. Increase labor in quantities and crafts. <br /> b. Increase the number of working hours per shift, shifts per working day, working days per week, <br /> or the amount of Equipment, or any combination of the foregoing. <br /> c. Reschedule activities. <br /> 2. If requested by the Owner's Representative,the Contractor shall prepare a proposed schedule revision <br /> demonstrating a plan to make up the lag in progress and insure completion of the Work within the <br /> Contract Time. All actions taken to return the Project to the accepted schedule are at the Contractor's <br /> expense. <br /> 3. The Contractor shall pay all costs incurred by the Owner that result from the Contractor's action to <br /> return the Project to its accepted schedule, including, but not limited to, additional, overtime, or third <br /> party inspection, design and construction management service costs. Contractor agrees that Owner <br /> shall deduct such charges from payments due the Contractor. It is further understood and agreed that <br /> none of the services performed by the Owner's Representative in monitoring,reviewing and reporting <br /> Project status and progress shall relieve the Contractor of responsibility for planning and managing <br /> construction Work in conformance with the construction schedule. <br /> E. Delays <br /> 1. General <br /> a. In the event of a Delay,the Contractor shall take immediate steps to minimize the Delay or avoid <br /> further Delay. The Contractor agrees it shall not make any Contract Claim or request for <br /> adjustment of Contract Time or Contract Sum based upon Delays for which it did not timely <br /> provide Notice to the Owner. <br /> 2. Bonuses u <br /> 10023829 City of Everett Public Works July 2018 <br /> WPCF FEN Chlorination Building Upgrade Work Order 3614 <br /> GENERAL.CONDITIONS <br /> 00 72 13-22 Issue for Bid ' <br />