1 <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> 8-02.3(16)A Lawn Installation — Sod <br /> (******) <br /> Install sod in irrigated areas only after the irrigation system is fully operational. <br /> Unless the Engineer approves otherwise, install sod between March 1 and <br /> October 1. Place sod strips within 48-hours of being cut. Place strips without <br /> voids and stagger the end joints. Roll sod with a smooth roller following <br /> placement to ensure good contact with the soil. <br /> During the establishment period, erect barriers, with warning signs where <br /> necessary, to preclude pedestrian traffic over the newly placed sod. <br /> Prepare areas for sod in accordance with standard horticultural practices as <br /> follows: <br /> 1. Rototill, or otherwise cultivate, to a minimum depth of 4-inches into the111 <br /> ground surface. Thoroughly incorporate a 10-2-10 fertilizer in the <br /> rototilling process at a rate of 4 pounds of available Nitrogen per 1000 <br /> square feet. <br /> 2. Rake the surface to even grade without low spots to trap water and round <br /> surface to match surroundings. <br /> 3. Add topsoil as required by the design. <br /> NOTE: Topsoil will be paid for separately if required. <br /> 4. Lightly dampen and compact the finished grade. <br /> 5. Install sod taking care to butt each piece tightly against the adjacent one. <br /> Stagger butt joints. Lay sod on sloped areas with the long dimension <br /> parallel to the toe or top of slope. After placing, roll the sod and sprinkle <br /> heavily with water. <br /> 6. Provide tools specially designed for the work and satisfactory to the <br /> Engineer. <br /> 7. Water and fertilize the sod during the 90 days establishment period. <br /> Schedule watering to prevent joints from drying between sod strips. <br /> Apply 6-2-4 fertilizer at 6 week intervals at the rate of 1 to 1-1/2 pounds <br /> of available Nitrogen per 1,000 square feet per application. <br /> Sod shall be used for restoration of established lawn, which must be removed to <br /> install the new storm drain pipe, and complete other Work described in the <br /> contract documents. The work shall consist of the removal and replacement of <br /> existing lawn turf by cutting the sod to be removed into convenient sized squares <br /> or strips to uniform thickness. piling and storing in a dampened condition, and <br /> finally replacing the sod in its original position. The Contractor may at his option <br /> use sod brought in from an outside source in lieu of replacing existing sod. If the <br /> Contractor elects to use sod from an outside source. the Engineer shall approve <br /> the supply source. <br /> The sod shall be removed to a uniform depth of approximately 2-inches with an <br /> approved type of sod cutter. This operation shall be performed in such a manner <br /> as to ensure uniform thickness of sod throughout the operation. <br /> Where sod is to be replaced with new sod, provide new sod in accordance with 9- <br /> 14.6(8) of these Special Provisions and the Standard Specifications. <br /> Guarantee sod to survive in a healthy condition through the 90 day establishment <br /> period. The establishment period shall begin on the date the Engineer accepts <br /> the sod placement. Remove and replace, at Contractor's expense, sod that in the <br /> opinion of the Engineer is not in a healthy growing condition at the end of the <br /> establishment period. Provide replacement sod that is of the same mixture and <br /> grade as the surviving sod. <br /> Alverson Stormwater Separation Division 8—MISC CONSTRUCTION February, 2019 <br /> WO No. -UP3660 SP—166 <br /> I <br />