The Contractor's request shall list the specific items of work that remain to be completed in <br /> order to reach physical completion. The Engineer will schedule an inspection of the work <br /> with the Contractor to determine the status of completion. The Engineer may also establish <br /> the Substantial Completion Date unilaterally. <br /> If, after this inspection, the Engineer concurs with the Contractor that the work is <br /> substantially complete and ready for its intended use, the Engineer, by written notice to the <br /> Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer <br /> does not consider the work substantially complete and ready for its intended use, the <br /> Engineer will, by written notice, so notify the Contractor giving the reasons therefor. <br /> Upon receipt of written notice concurring in or denying substantial completion, whichever is <br /> applicable, the Contractor shall pursue vigorously, diligently and without unauthorized <br /> interruption, the work necessary to reach Substantial and Physical Completion. The <br /> Contractor shall provide the Engineer with a revised schedule indicating when the <br /> Contractor expects to reach substantial and physical completion of the work. <br /> The above process shall be repeated until the Engineer establishes the Substantial <br /> Completion Date and the Contractor considers the work physically complete and ready for <br /> final inspection. <br /> 1-05.11(2) Final Inspection and Physical Completion Date <br /> When the Contractor considers the work physically complete and ready for final inspection, <br /> the Contractor by written notice, shall request the Engineer to schedule a final inspection. <br /> The Engineer will set a date for final inspection. The Engineer and the Contractor will then <br /> make a final inspection and the Engineer will notify the Contractor in writing of all particulars <br /> in which the final inspection reveals the work incomplete or unacceptable. The Contractor <br /> shall immediately take such corrective measures as are necessary to remedy the listed <br /> deficiencies. Corrective work shall be pursued vigorously, diligently, and without interruption <br /> until physical completion of the listed deficiencies. This process will continue until the <br /> Engineer is satisfied the listed deficiencies have been corrected. <br /> If action to correct the listed deficiencies is not initiated within 7 days after receipt of the <br /> written notice listing the deficiencies, the Engineer may, upon written notice to the <br /> Contractor, take whatever steps are necessary to correct those deficiencies pursuant to <br /> Section 1-05.7. <br /> The Contractor will not be allowed an extension of contract time because of a delay in the <br /> performance of the work attributable to the exercise of the Engineer's right hereunder. <br /> Upon correction of all deficiencies, the Engineer will notify the Contractor and the <br /> Contracting Agency, in writing, of the date upon which the work was considered physically <br /> complete. That date shall constitute the Physical Completion Date of the contract, but shall <br /> not imply acceptance of the work or that all the obligations of the Contractor under the <br /> contract have been fulfilled. <br /> Swift Green Line—Corridor Stations Special Provisions SP23 <br /> May 2017 <br />