1-05.15 Method of Serving Notices <br /> (March 25, 2009 APWA GSP) <br /> Revise the second paragraph to read: <br /> All correspondence from the Contractor shall be directed to the Project Engineer. All <br /> correspondence from the Contractor constituting any notification, notice of protest, notice of <br /> dispute, or other correspondence constituting notification required to be furnished under the <br /> Contract, must be in paper format, hand delivered or sent via mail delivery service to the <br /> Project Engineer's office. Electronic copies such as e-mails or electronically delivered copies <br /> of correspondence will not constitute such notice and will not comply with the requirements <br /> of the Contract. <br /> Add the following new section: <br /> 1-05.16 Water and Power <br /> (October 1, 2005 APWA GSP) <br /> The Contractor shall make necessary arrangements, and shall bear the costs for power and <br /> water necessary for the performance of the work, unless the contract includes power and <br /> water as a pay item. <br /> Add the following new section: <br /> 1-05.18 Record Drawings NEW <br /> The Contractor shall maintain one set of half size (11x17) plans for Record Drawings, <br /> updated with clear and accurate red-lined field revisions on a daily basis, and within 2 <br /> business days after receipt of information that a change in Work has occurred. The <br /> Contractor shall not conceal any work until the required information is recorded. <br /> This Record Drawing set shall be used for this purpose alone, shall be kept separate from <br /> other Plan sheets, and shall be clearly marked as Record Drawings. These Record <br /> Drawings shall be kept on site at the Contractor's field office, and shall be available for <br /> review by the Contracting Agency at all times. <br /> The preparation and upkeep of the Record Drawings is to be the assigned responsibility of a <br /> single, experienced, and qualified individual. The quality of the Record Drawings, in terms <br /> of accuracy, clarity, and completeness, is to be adequate to allow the Contracting Agency to <br /> modify the computer-aided drafting (CAD) Contract Drawings to produce a complete set of <br /> Record Drawings for the Contracting Agency without further investigative effort by the <br /> Contracting Agency. <br /> The Record Drawing markups shall document all changes in the Work, both concealed and <br /> visible. Items that must be shown on the markups include but are not limited to: <br /> • Actual dimensions, arrangement, and materials used when different than shown in the <br /> Plans. <br /> Swift Green Line—Corridor Stations Special Provisions SP26 <br /> May 2017 <br />