No other work shall be performed on the site until the Contracting Agency has accepted the <br /> installation of high visibility fencing, as described in the Contract. <br /> Section 1-08.4 is supplemented with the following: <br /> 1-08.4(1) Sequence of Construction <br /> The sequence and limitations of construction are dictated by the specific characteristics of <br /> the Work and the Site. The Contractor shall comply with and include in its Construction <br /> Schedule the limitations of Work specified in this Section. <br /> The Contractor must plan and sequence the work in a logical sequence. <br /> The contractor shall not leave any site open for more than three weeks without the approval <br /> of Community Transit unless this intent is clearly shown in the construction schedule and <br /> approved by Community Transit when the specific site construction is occurring. A site open <br /> is defined as a site being worked on by the contractor between initial clearing stage and <br /> placement of platform, driveway and sidewalk concrete. If the site platform has been placed, <br /> but the column footing access closure pours have not occurred, the site will not be <br /> considered open. It is not the intent of this construction to open a site, perform clearing and <br /> grading, and then let it sit open for an extended period of time before surfacing and paving is <br /> performed. <br /> Sequence of Work: <br /> 1. The Contractor shall commence work immediately upon Notice to Proceed (NTP) and <br /> pursue the Work in an orderly fashion such that the Physical Completion date is met. <br /> The Work requires careful sequencing to properly coordinate the Work with activities <br /> related to compliance with permits from local and state agencies, and proper sequencing <br /> of construction activities. <br /> 2. The contractor shall not leave any Station site open for more than four(4)weeks without <br /> the approval of Community Transit unless this intent is clearly shown in the construction <br /> schedule and approved by Community Transit. A site open is defined as a site being <br /> worked on by the contractor between initial clearing stage and placement of platform, <br /> driveway and sidewalk concrete. If the site platform has been placed, but the column <br /> footing access closure pours have not occurred, the site will not be considered open. It <br /> is not the intent of this construction to open a site, perform clearing and grading, and <br /> then let it sit open for an extended period of time before surfacing and paving is <br /> performed. <br /> 3. No work requiring lane closures shall occur on Northbound and Southbound Station <br /> pairs concurrently unless previously reviewed and approved by the Engineer and the <br /> applicable jurisdiction(s). <br /> 4. Canyon Park Park & Ride—Temporary closure of parking stalls along the southern row <br /> of the Park & Ride (adjacent to new sidewalk), and of the parallel stalls along the drive <br /> aisle shall be limited in duration to 60 calendar days in order to minimize temporary <br /> parking impacts. <br /> 5. Roadway Widening on SR 527 at 164th Street SE (Penny Creek Crossing area)— <br /> Construction of roadway widening in this area shall be scheduled for completion during <br /> May 1st through September 30th. <br /> Swift Green Line—Corridor Stations Special Provisions SP58 <br /> May 2017 <br />