Laserfiche WebLink
City of Everett 00 7200 - 34 ' <br /> 2019 Biosolids Removal UT3705-2 <br /> 9.5. ADJUSTMENT OF CONTRACT SUM <br /> 9.5.1 Calculation <br /> Except as otherwise expressly provided in these General Conditions, any and all adjustments of Contract i <br /> Sum shall be determined as follows: <br /> 1. If the parties are able to agree,the price will be determined by using: <br /> a. Unit prices, if the Work items are defined by unit prices; and <br /> b. Other prices agreed upon by the Contractor and Owner for Work not defined by unit prices. <br /> 2. If the parties cannot agree,the Owner's Representative will determine the price pursuant to the <br /> following order: <br /> a. Unit prices, if the Work items are defined by unit prices; and ' <br /> b. Other means to establish the reasonable cost of the Work if it is not defined by unit prices, <br /> including, but not limited to,Force Account as described in 9.6. FORCE ACCOUNT, the <br /> Schedule of Values, or estimating manuals. <br /> 9.5.2 Limitations <br /> The following limitations shall apply in determining the amount of an adjustment: <br /> 1. Except as otherwise expressly provided,Contractor will only be paid for costs it clearly and • <br /> convincingly proves it actually and directly incurred,and shall not include consequential or indirect <br /> damages not otherwise expressly permitted by the Contract Documents. Costs and damages for <br /> which Owner shall not be liable under any circumstances include,but are not limited to: (a) <br /> borrowing or interest costs,charges,or expenses of Contractor; (b)alleged lost profit or Overhead <br /> on any other project; and(c)Contractor's failure or inability to obtain other work. <br /> 2. No Contract Claim for adjustment of Contract Sum or additional compensation for extra, affected, <br /> impacted or inefficient Work will be allowed where the Contractor does not keep and maintain <br /> contemporaneous, complete and accurate time records for labor and equipment and <br /> contemporaneous,complete and accurate records for materials and where such records do not <br /> contemporaneously segregate and allocate by time, location and work the time and costs for each <br /> item or element of such work.Contractor's failure to keep and maintain such records constitutes a <br /> waiver of any Contract Claim or request by the Contractor for adjustment of Contract Sum for such 111 <br /> costs or event. <br /> 3. To the extent the Contractor is entitled to an adjustment of Contract Sum due to any Delay or <br /> extension of Contract Time,Contractor shall be compensated as provided in 12.4 REMEDIES. <br /> Such compensation shall be full,adequate and complete compensation for all direct, indirect, <br /> cumulative, inefficiency, impact and ripple costs causing,arising out of, or relating to such delays <br /> or extension. <br /> 4. Contractor and Owner agree that compensation to the Contractor for a Contract Claim shall not <br /> exceed the Contractor's costs based upon Force Account as described in 9.6.FORCE ACCOUNT. <br /> Contractor waives,releases,and agrees not to submit any request for adjustment of Contract Sum or <br /> Contract Claim based upon a"total cost'or"modified total cost"calculation, in whole or in part, <br /> but instead agrees that any and all requests for compensation shall be based upon accurate, complete <br /> and contemporaneous cost records that segregate and allocate costs(a)between base Contract Work <br /> and the work for which additional compensation is sought and(b)between each item of work for <br /> which additional compensation is sought. Claims for inefficiency shall only be based and <br /> calculated by a comparison of productivity of similar Work performed in an unaffected or least <br /> affected area of the Project. <br /> 5. No claim for consequential damages of any kind will be allowed. <br /> 00 7200 - 34 GENERAL CONDITIONS , <br />