Laserfiche WebLink
City of Everett 00 7200 -22 I <br /> 2019 Biosolids Removal UT3705-2 <br /> If the Contractor and Owner do not agree upon scope of Work changed or adjustment to the Contract Sum <br /> and Contract Time,the Owner may, at its sole option,unilaterally direct the Contractor to implement any <br /> change by notice. The Owner shall not pay or be responsible or liable for any change implemented by the <br /> Contractor without explicit notice from the Owner to proceed. <br /> 6.2 EXTRA WORK <br /> At its sole option,the Owner may(1)perform Extra Work itself, (2)employ others to do it, (3) direct the I <br /> Contractor to perform the Extra Work at existing unit bid price, (4)direct the Contractor to perform the <br /> Extra Work at a mutually agreed upon price, or(5)direct the Contractor to perform the Extra Work on a <br /> Force Account basis. <br /> 6.3 CHANGE ORDERS <br /> Changes to the Work may result in an increase or decrease in Contract Sum, as provided in 9.2. ' <br /> PAYMENT FOR CHANGES. Requests for an increase in Contract Time must be made as provided in <br /> 5.2.2.2 Extensions of Contract Time, as applicable. Substantial changes in Contract Time, Contract <br /> Sum or Work will often be negotiated and agreed between the Contractor and Owner before the Owner <br /> directs the Contractor to proceed with the change. <br /> If the Contractor and Owner agree on the scope of Work and any changes to Contract Sum and Contract <br /> Time,the Contractor and Owner shall execute an agreed Change Order. However, if the Contractor and I <br /> Owner do not agree,the Owner may, in its sole discretion, issue a unilateral Change Order changing the <br /> scope of Work and making any adjustments to the Contract Sum pursuant to 9.2.PAYMENT FOR <br /> CHANGES and Contract Time in such amount and for such time as the Owner thinks appropriate. <br /> Contractor agrees to use the agreed and unilateral Change Order attached to these General Conditions or <br /> otherwise provided by Owner. The Contractor accepts all requirements,terms and conditions of a <br /> Change Order by: signing it; writing a separate acceptance; or by failing to notify the Owner immediately <br /> in writing that Contractor disagrees with the Change Order and does not intend to be bound by its terms. <br /> The Contractor waives and is estopped from denying its agreement with any unilateral Change Order for <br /> which the Contractor does not immediately give Notice to the Owner as provided in ARTICLE 10. <br /> NOTICE TO OWNER and submitting a Contract Claim as provided in ARTICLE 12. CONTRACT <br /> CLAIMS. A unilateral Change Order that is not timely protested as provided in this section shall be full <br /> payment and final settlement of all asserted and unasserted Contract Claims for Contract Time and all <br /> costs of any kind, including costs of Delays, inefficiencies and impacts, related to,arising out of, or <br /> resulting from, any Work described in the Change Order. <br /> The Contractor shall obtain written consent of the surety or sureties if the Owner's Representative <br /> requests such consent. <br /> 6.4 VALUE ENGINEERING AND COST SHARING <br /> The Contractor may submit proposals for changing the Drawings, Specifications,or other requirements of <br /> the Contract Documents and the Owner, in its sole discretion, may accept or reject such proposals. If <br /> accepted by the Owner and if the proposal decreases the direct, actual costs of constructing the Work,the <br /> Contract Sum shall be reduced by fifty percent(50%)of the direct, actual construction cost saved. <br /> Because the Owner has the sole discretion whether to consider, accept or reject the Contractor's proposal <br /> and the Contractor has no right to require the Owner to consider or accept such proposals,the Owner's <br /> decision is not reviewable by any court. This subsection applies only to change proposals initiated solely <br /> by the Contractor(or its Subcontractors and Suppliers)and does not apply to change proposals requested <br /> or initiated by the Owner or the Owner's Representative. The Owner is not obligated or required to <br /> consider any Contractor initiated change proposals and may, in its sole discretion, refuse to do so. Under I <br /> no circumstances shall the Contractor be entitled to additional compensation arising out of, or related to, <br /> the Owner's refusal to consider or approve a Contractor initiated change proposal. The Contractor shall <br /> not do any of the following without the express written agreement of the Owner: fail to perform any <br /> Work; commence performance of any proposed change; reduce its resources assigned to performance of <br /> 00 7200 - 22 GENERAL CONDITIONS , <br />